Energy BOE Importance: 3/10

Bordecorex Norte photovoltaic solar installation in Soria denied due to permit expiration

16 Oct 2026 Effective: 16 Oct 2026 0 views
Who is affected:
Renewable energy developers and investors in photovoltaic and hybrid projects in Spain

Summary

The General Directorate of Energy Policy denies Biovent Energía the construction of a 44 MW solar plant in Soria as its grid access permits have expired.

Detailed analysis PRO

The General Directorate of Energy Policy and Mines rejects the application by Biovent Energía, SA to build a 44.199 MW photovoltaic installation in Soria intended to be hybridized with the Bordecorex Norte wind farm. The main reason is the expiration, on May 10, 2026, of the access and connection permits to the Almazán…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 9 de septiembre de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Biovent Energía, SA, de autorización administrativa previa y autorización de construcción de la instalación fotovoltaica Bordecorex Norte, de 44,199 MW de potencia instalada, para su hibridación con el parque eólico Bordecorex Norte, de 44,35 MW de potencia instalada, en la provincia de Soria.