Iberdrola cannot build the Ventosa del Ducado solar plant in Soria due to permit expiration

16 Oct 2026 Effective: 16 Oct 2026 0 views
Who is affected:
Iberdrola Renovables Castilla y León and renewable energy project developers

Summary

The Ministry denies Iberdrola authorization for a 43.89 MW solar plant in Soria as its electrical grid access permits expire. The hybrid solar-wind project is permanently halted.

Detailed analysis PRO

The Directorate General for Energy Policy and Mines dismisses Iberdrola Renovables Castilla y León's request to build a 43.89 MW photovoltaic installation in Miño de Medinaceli (Soria), intended to be hybridized with the existing 44 MW wind farm. The determining cause is the expiration, on May 10, 2026, of access and c…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 9 de septiembre de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Iberdrola Renovables Castilla y León, SA, de autorización administrativa previa y autorización administrativa de construcción de la instalación fotovoltaica Ventosa del Ducado, de 43,89 MW de potencia instalada, para su hibridación con el parque eólico Ventosa del Ducado, de 44 MW de potencia instalada, en la provincia de Soria.

Related regulations