Energy BOE Importance: 3/10

Photovoltaic expansion of 'La Zarzuela' plant in Burgos denied due to change in administrative competence

09 Nov 2026 Effective: 09 Nov 2026 0 views
Who is affected:
Renewable energy development companies and hybrid wind-photovoltaic installations

Summary

The State denies authorization for a 13.685 MW solar plant in Burgos because the promoter reduced the power to 0.3 MW, losing state competence.

Detailed analysis PRO

The Directorate General for Energy Policy and Mines dismisses the application by CYL Energía Eólica to hybridize the 'La Zarzuela' wind farm with a 13.685 MW photovoltaic plant in Burgos. The reason is that during the public hearing procedure, the promoter reduced the photovoltaic power to 0.3 MW, leaving the total pow…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 22 de octubre de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de CYL Energía Eólica, SLU, de autorización administrativa previa, autorización administrativa de construcción y declaración, en concreto, de utilidad pública para la planta fotovoltaica «La Zarzuela», de 13,685 MW de potencia instalada, para su hibridación con el parque eólico existente «La Zarzuela», de 41,8 MW, y una parte de su infraestructura de evacuación, en Castrojeriz y Los Balbases (Burgos).

Related regulations