Public utility declaration for Navabuena Solar 449 MW solar plant in Valladolid
31 Jul 2026Effective: 31 Jul 202644 views
Who is affected:
Landowners affected in Valladolid, La Mudarra and Villalba de los Alcores
Summary
The Government declares the Navabuena Solar photovoltaic plant in Valladolid, with 449 MW of power, to be of public utility. This allows the developer to occupy land to build the installation and its evacuation lines.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Navabuena Solar, SL the public utility declaration for a large photovoltaic plant of 449.148 MW peak and 424.710 MW installed in Villalba de los Alcores, La Mudarra and Valladolid. This declaration legally enables the developer to occupy public and private doma…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 6 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Navabuena Solar, SL, la declaración, en concreto, de utilidad pública, para la instalación fotovoltaica «Navabuena Solar», de 449,148 MW de potencia pico, 424,710 MW de potencia instalada, y sus infraestructuras de evacuación, en Villalba de los Alcores, La Mudarra y Valladolid (Valladolid).
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection
Naturgy Renovables withdraws its application to build a 39 MW photovoltaic plant and 20 MW battery in Valladolid. The Ministry accepts the withdrawal and closes...
Naturgy Renovables SLU and photovoltaic project developers in state processing