Authorization to install a 39.6 MW battery system next to the Afrodita solar plant in Seville
18 Aug 2026Effective: 18 Aug 2026107 views
Who is affected:
Renewable energy sector companies, solar plant and storage developers
Summary
Afrodita Solar is authorized to build a 39.6 MW battery storage module in Los Molares (Seville) to hybridize it with its existing 46.2 MW solar park.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Afrodita Solar, SL, prior administrative and construction authorization for a 39.6 MW BESS system in Los Molares (Seville). The installation will be hybridized with the existing 'Afrodita' photovoltaic park of 46.2 MW, leveraging its evacuation infrastructure t…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 31 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Afrodita Solar, SL, autorización administrativa previa y autorización administrativa de construcción del módulo de almacenamiento por baterías «Bess Afrodita», de 39,6 MW de potencia instalada, y para su infraestructura de evacuación, para su hibridación con el parque solar fotovoltaico existente «Afrodita», de 46,2 MW de potencia instalada, en Los Molares (Sevilla).
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
The EU corrects translation errors in model contractual clauses so that importers of oil, gas and coal can demonstrate compliance with methane pollution control...
European importers of crude oil, natural gas, LNG and coal, and their foreign suppliers
The Government authorizes Red Eléctrica to build a new 400 kV electrical substation in Isona (Lleida) and declares the work of public utility. The installation ...
Red Eléctrica de España, owners of affected properties in Isona i Conca Dellà (Lleida)
Naturgy Renovables withdraws its application to build a 39 MW photovoltaic plant and 20 MW battery in Valladolid. The Ministry accepts the withdrawal and closes...
Naturgy Renovables SLU and photovoltaic project developers in state processing
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection