Energy BOE Importance: 3/10

Authorization to build the new Isona 400 kV electrical substation in Lleida

18 Aug 2026 12 views
Who is affected:
Red Eléctrica de España, owners of affected properties in Isona i Conca Dellà (Lleida)

Summary

The Government authorizes Red Eléctrica to build a new 400 kV electrical substation in Isona (Lleida) and declares the work of public utility. The installation is part of the Electrical Transport Plan 2021-2026.

Detailed analysis PRO

The General Directorate of Energy Policy and Mines grants Red Eléctrica de España, SAU, prior administrative authorization for modifications and construction of the Isona 400 kV substation and its entry/exit line in the province of Lleida. The declaration of public utility enables forced expropriation of affected land,…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 27 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Red Eléctrica de España, SAU, autorización administrativa previa de modificaciones y autorización administrativa de construcción para la nueva subestación Isona 400 kV y la línea de entrada/salida a 400 kV en la subestación Isona 400 kV de la línea Sentmenat-Sallente, en la provincia de Lleida, y se declara, en concreto, la utilidad pública.

Sponsored space
Sponsor the Energy category

Your brand in front of thousands of businesses and freelancers tracking the legal changes in your sector.

I want to sponsor it

Related regulations