Energy BOE Importance: 3/10

Authorization to install energy storage batteries next to solar plant in Alcalá de Guadaíra (Seville)

19 Aug 2026 4 views
Who is affected:
Gestenia Energía SL and renewable energy sector in Andalusia

Summary

The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better storage and management of generated renewable energy.

Detailed analysis PRO

The General Directorate of Energy Policy and Mines grants Gestenia Energía, SL, prior and construction authorization to hybridize its photovoltaic park 'GES' (46.2 MW) with a BESS battery storage module of 39.6 MW in Alcalá de Guadaíra. The project is covered by the simplified procedure of RD 997/2025, which exempts st…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 31 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Gestenia Energía, SL, autorización administrativa previa y autorización administrativa de construcción del módulo de almacenamiento por baterías «BESS GES», de 39,6 MW de potencia instalada, y para su infraestructura de evacuación, para su hibridación con el parque solar fotovoltaico existente «Ges», de 46,2 MW de potencia instalada, en Alcalá de Guadaíra (Sevilla).