Energy BOE Importance: 4/10

Allocation of 320 MW of renewable capacity at the Narcea 400 kV electrical node to La Barca Energía

29 Jul 2026 Effective: 29 Jul 2026 58 views
Who is affected:
Renewable generation companies, energy developers and just transition territories in Asturias

Summary

The Government allocates to La Barca Energía the capacity for access to the electrical grid at Narcea (Asturias) to install 320 MW of renewable generation. The project promotes just transition in a mining area undergoing restructuring.

Detailed analysis PRO

The State Secretariat for Energy resolves the Narcea 400 kV node competition by allocating 320 MW of MGES capacity to La Barca Energía, SL, with its CHR La Barca project, which obtained 85.82 points against EDP España (49.65) and CDR Buseiro (30.91). The total capacity tendered was 354 MW for MGES and 354 MW for MPE, p…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 10 de julio de 2026, de la Secretaría de Estado de Energía, por la que se resuelve el concurso público para la concesión de capacidad de acceso de evacuación a la red de energía eléctrica de instalaciones de generación de electricidad de procedencia renovable en el nudo de transición justa Narcea 400 kV.