Key data
| Regulation | Resolution of September 9, 2026, from the General Directorate of Energy Policy and Mines |
|---|---|
| BOE Publication | October 16, 2026 |
| Entry into force | October 16, 2026 |
| Affected promoter | Biovent Energía, SA |
| Installation | Bordecorex Norte Photovoltaic (hybridization with homonymous wind farm) |
| Requested photovoltaic capacity | 44,199 MW |
| Associated wind capacity | 44.35 MW |
| Location | Province of Soria |
| Connection substation | Almazán 400 kV (Red Eléctrica) |
| Grid permission expiration date | May 10, 2026 |
| Key regulations involved | RDL 23/2020 and RDL 20/2022 |
| Category | Energy |
A project of 44,199 MW photovoltaic in Soria, designed to hybridize with the Bordecorex Norte wind farm (44.35 MW), is eliminated before construction. The Resolution of September 9, 2026 from the General Directorate of Energy Policy and Mines dismisses the request from Biovent Energía, SA, published in the BOE on October 16, 2026.
It is not a denial for technical or substantive environmental reasons: it is a denial due to expiration of grid access and connection permits. A timing problem that, according to the resolution itself, is a frequent bottleneck in the Spanish renewable sector.
What does this resolution establish?
The resolution dismisses the request for prior administrative authorization and construction authorization of the Bordecorex Norte photovoltaic installation. The chain of events leading to this denial is as follows:
- Project: 44,199 MW solar plant to hybridize with the Bordecorex Norte wind farm (44.35 MW) in the province of Soria.
- Planned connection: Almazán 400 kV substation, managed by Red Eléctrica.
- First obstacle: The simplified environmental assessment was filed for not meeting the requirements established by RDL 20/2022.
- Second obstacle (definitive): Access and connection permits to the Almazán 400 kV substation expired on May 10, 2026, as the environmental impact declaration was not obtained within the deadline required by RDL 23/2020.
- Legal consequence: Without valid access and connection permits, current regulations prohibit granting administrative authorization. The resolution has no alternative: it must dismiss.
The regulatory framework applied combines RDL 23/2020 (which sets deadlines for obtaining the environmental impact declaration as a condition to maintain grid permits) and RDL 20/2022 (which establishes additional requirements for simplified environmental assessment). Non-compliance with either deadline triggers automatic loss of connection permits.
Economic and operational impact
The denial of Bordecorex Norte illustrates a systemic risk for the Spanish renewable sector: the desynchronization between grid permit deadlines and environmental procedure deadlines.
Access and connection permits to the grid have limited validity. If the environmental impact assessment (EIA) procedure extends beyond that deadline—something common given the volume of pending cases—grid permits expire and the project is blocked without possibility of authorization, regardless of its technical or environmental viability.
The economic consequences for a promoter in this situation are:
- Loss of all investment made in engineering, environmental studies, and administrative processing.
- Need to restart the grid permit request process from scratch, with new access queues.
- Risk of losing the position at the connection substation, which may have been assigned to other projects.
- Reputational impact with project investors and financiers.
The resolution expressly notes that this type of situation—grid permit expiration due to delays in environmental processing—is a frequent bottleneck in the Spanish renewable sector, indicating that Bordecorex Norte is not an isolated case.
Who does it affect?
- Promoters of photovoltaic projects with valid or soon-to-expire access and connection permits.
- Promoters of hybrid solar-wind projects, where hybridization adds an additional processing layer.
- Investors and renewable infrastructure funds with projects in portfolio in environmental processing phase.
- Legal and technical advisors managing authorization files for renewable installations.
- CFOs and business development directors in energy companies with project pipelines in Spain.
- Financing entities (banks, funds) evaluating regulatory risk of renewable projects in construction phase.
Practical example
The case of Biovent Energía is the real example. The company obtained access and connection permits to connect its 44,199 MW photovoltaic plant to the Almazán 400 kV substation of Red Eléctrica, in the province of Soria. Those permits had a deadline linked to obtaining the environmental impact declaration, according to RDL 23/2020.
In parallel, the simplified environmental assessment was filed for not meeting the requirements of RDL 20/2022, further delaying the procedure. The result: when May 10, 2026 arrived, grid permits expired without an environmental impact declaration existing. From that point on, the General Directorate of Energy Policy and Mines had no legal margin to grant authorization, and the dismissal resolution was inevitable.
A promoter in a similar situation—with grid permits about to expire and EIA in processing—must urgently verify if their deadlines are aligned, or request extensions before expiration occurs.
What should companies do now?
- Audit the status of all access and connection permits in portfolio: Identify the expiration date of each permit and the status of the associated environmental procedure. Desynchronization between both deadlines is the main risk.
- Verify compliance with RDL 20/2022 requirements for simplified environmental assessment: Filing of the case for non-compliance with formal requirements, as happened in Bordecorex Norte, can cost critical months of processing.
- Calculate the real time margin between grid permit expiration and the expected date for obtaining the EIA: If the margin is less than 6 months, activate preventive measures (request for extension, acceleration of environmental case, communication with the competent environmental authority).
- Review contracts with advisors and case managers: Establish automatic alerts for grid permit expiration and environmental procedure milestones.
- Inform investors and financiers: If there are projects in portfolio with risk of permit expiration, communicate it proactively with the mitigation plan, before the denial materializes.
Frequently asked questions
Why was the Bordecorex Norte photovoltaic denied if the project was technically viable?
The denial was not for technical or substantive environmental reasons, but due to expiration of access and connection permits to the Almazán 400 kV substation of Red Eléctrica. Those permits expired on May 10, 2026 because the environmental impact declaration was not obtained within the deadline required by RDL 23/2020. Without valid grid permits, the law prohibits granting administrative authorization.
What deadline does RDL 23/2020 set for obtaining the environmental impact declaration and not losing grid permits?
RDL 23/2020 establishes that access and connection permits to the grid have validity conditioned on obtaining the environmental impact declaration within a determined deadline. In the case of Bordecorex Norte, that deadline expired on May 10, 2026 without the EIA having been obtained, which caused automatic expiration of the permits. The specific deadline applicable to each project depends on its request date and the regulations in force at that time.
What happened with the simplified environmental assessment of Bordecorex Norte?
The simplified environmental assessment was previously filed for not meeting the requirements established in RDL 20/2022. This filing delayed the environmental procedure and contributed to the environmental impact declaration not being obtained before the grid permits expired on May 10, 2026.
Can Biovent Energía request authorization for the Bordecorex Norte photovoltaic project again?
The resolution dismisses the current request. To restart the project, Biovent Energía would need to request new grid access and connection permits from scratch, which means returning to the access queue and assuming the deadlines and costs associated with a new complete case. The resolution does not contemplate any remedy or extension route.
Does this resolution affect the Bordecorex Norte wind farm, which was already in operation or processing?
The resolution refers exclusively to the 44,199 MW photovoltaic installation requested to hybridize with the Bordecorex Norte wind farm (44.35 MW). The resolution does not mention any direct impact on the existing or processing wind farm. The impact is limited to the solar project and the planned hybridization.