Energy

22 MW Solar Plant in Ávila: Authorization for Hybridization with Wind Farm

E
Equipo Editorial CambiosLegales
Nov 16, 2026 6 min 15 views

Key data

RegulationResolution of 23 October 2026, from the General Directorate of Energy Policy and Mines
Publication16 November 2026
Entry into force16 November 2026
PromoterEólica Sierra de Ávila, SL
Authorized installationColladillo photovoltaic plant, 22.05 MW
Wind farm to be hybridizedColladillo wind farm, 30.06 MW
MunicipalitiesPadiernos and Niharra (Ávila)
EvacuationLastras 400 kV substation (Red Eléctrica de España)
Regulatory frameworkRoyal Decree 1955/2000
Favorable EIA28 August 2026
CategoryEnergy
Year2026
Impact analysis reserved for subscribers
The detailed impact analysis of this regulation is available with the PRO and Business plans. Access the full content and receive personalized alerts.
From €9.99/month · Cancel anytime

Eólica Sierra de Ávila, SL can begin construction of the Colladillo photovoltaic installation after receiving prior administrative authorization from the General Directorate of Energy Policy and Mines, published on 16 November 2026. The plant, with 22.05 MW of installed capacity, will be located in the municipalities of Padiernos and Niharra (Ávila) and will be hybridized with the Colladillo wind farm, with 30.06 MW, already registered in the administrative registry.

The processing was carried out jointly with the solar project Cabeza Mesá (27.3 MW), under the framework of Royal Decree 1955/2000. The resolution is not the operating authorization: the promoter must still comply with a series of conditions before being able to start up the installation.

22.05 MW
Authorized photovoltaic capacity
30.06 MW
Capacity of the wind farm to be hybridized
27.3 MW
Cabeza Mesá solar project processed jointly
400 kV
Evacuation voltage at Lastras substation (REE)

What does this regulation establish?

The resolution grants prior administrative authorization —the first formal step in the authorization process for electrical installations in Spain— for the Colladillo photovoltaic plant. This phase allows the promoter to continue with construction procedures, but does not yet enable commercial operation.

The key technical elements and conditions established by the resolution are:

ElementDetail
Authorized installationColladillo photovoltaic plant, 22.05 MW
Hybridization withColladillo wind farm, 30.06 MW (already registered in administrative registry)
Joint processingCabeza Mesá solar project, 27.3 MW
Applied regulatory frameworkRoyal Decree 1955/2000
Environmental Impact StatementFavorable, issued on 28 August 2026
Landscape conditionProgram of compensatory measures with landscape integration, approved by the Junta de Castilla y León, prior to operating authorization
Hydrological conditionConditions from the Duero River Basin Authority
Road conditionAnti-glare measures on the N-502
Evacuation pointLastras 400 kV substation, Red Eléctrica de España

The favorable environmental impact statement (EIA), issued on 28 August 2026, imposes preventive, corrective and compensatory measures that are mandatory. Without approval of the program of compensatory measures with landscape integration by the Junta de Castilla y León, the promoter will not be able to obtain operating authorization.

Economic and operational impact

For Eólica Sierra de Ávila, SL, this resolution unlocks the next phase of the project and allows progress toward construction. However, project profitability is conditioned on compliance with the following operational milestones:

  • Development and approval of the program of compensatory measures with landscape integration before the Junta de Castilla y León: a prerequisite and unavoidable requirement for operating authorization.
  • Compliance with the conditions of the Duero River Basin Authority: affects the design and execution of the evacuation infrastructure.
  • Installation of anti-glare measures on the N-502: additional civil works cost that must be integrated into the project budget.
  • Coordination with Red Eléctrica de España for connection to the Lastras 400 kV substation: REE timelines may condition the startup date.

Photovoltaic-wind hybridization allows optimization of the use of the existing grid connection point of the wind farm, reducing evacuation infrastructure costs and maximizing generation hours at the node. This hybridization model is one of the most efficient in terms of grid access capacity utilization.

Who does it affect?

  • Eólica Sierra de Ávila, SL: direct promoter. Must manage all imposed conditions before requesting operating authorization.
  • Local administrations of Padiernos and Niharra (Ávila): municipalities where the installation will be located; may be involved in urban planning licenses and environmental monitoring procedures.
  • Red Eléctrica de España (REE): responsible for the Lastras 400 kV substation, the evacuation point for generated energy.
  • Junta de Castilla y León: must approve the program of compensatory measures with landscape integration.
  • Duero River Basin Authority: issues binding conditions for the evacuation infrastructure.
  • Renewable energy sector companies interested in solar-wind hybridization projects in Spain: this case is a reference for the applicable procedure under Royal Decree 1955/2000.

Practical example

Eólica Sierra de Ávila, SL already operates the Colladillo wind farm with 30.06 MW connected to the Lastras 400 kV substation. With the new 22.05 MW photovoltaic plant, the connection node will manage a combined capacity of over 52 MW without needing to build new evacuation infrastructure from scratch.

However, before the solar plant can generate and feed energy into the grid, the promoter must:

  1. Draft the program of compensatory measures with landscape integration and obtain approval from the Junta de Castilla y León.
  2. Resolve the conditions of the Duero River Basin Authority regarding the evacuation infrastructure.
  3. Execute the anti-glare measures required on the affected section of the N-502.
  4. Coordinate with REE the effective connection to the Lastras 400 kV substation.

Only after completing these steps can the promoter request operating authorization, which is what enables energy generation and sale.

Do you need to monitor this and other regulations?

Check the full details on CambiosLegales

What should companies do now?

  1. Eólica Sierra de Ávila, SL: immediately begin development of the program of compensatory measures with landscape integration to present to the Junta de Castilla y León, since its approval is a prerequisite for operating authorization.
  2. Review and address the conditions of the Duero River Basin Authority regarding evacuation infrastructure, integrating them into the construction project.
  3. Plan and budget the anti-glare measures on the N-502 as a specific line item in the construction project.
  4. Coordinate with Red Eléctrica de España the timelines and technical requirements for connection to the Lastras 400 kV substation, given that REE timelines may be determining factors in the startup schedule.
  5. Renewable energy sector companies with hybridization projects: analyze this case as a reference for the procedure under Royal Decree 1955/2000 and the usual conditions in joint processing of solar and wind projects in Castilla y León.

Frequently asked questions

What is the difference between prior administrative authorization and operating authorization?

Prior administrative authorization, which is what this resolution grants, allows the promoter to continue with procedures and installation construction. Operating authorization is what enables startup and commercial energy generation. In this case, Eólica Sierra de Ávila will not be able to operate the solar plant until obtaining that second authorization, for which it must first comply with the environmental, landscape and hydrological conditions imposed.

What conditions must Eólica Sierra de Ávila comply with before operating the solar plant?

The promoter must: (1) develop a program of compensatory measures with landscape integration approved by the Junta de Castilla y León; (2) comply with the conditions of the Duero River Basin Authority regarding evacuation infrastructure; (3) install anti-glare measures on the N-502; and (4) coordinate connection to the Lastras 400 kV substation with Red Eléctrica de España.

Why was it processed jointly with the Cabeza Mesá solar project?

The resolution indicates that processing was carried out jointly with the Cabeza Mesá solar project (27.3 MW) under Royal Decree 1955/2000. This type of joint processing is common when projects share evacuation infrastructure or are developed in the same geographic area, allowing for more efficient environmental and administrative evaluation.

What is the total capacity of the generation node after hybridization?

Hybridization combines the Colladillo photovoltaic plant (22.05 MW) with the Colladillo wind farm (30.06 MW), which represents a combined installed capacity exceeding 52 MW at the same evacuation point: the Lastras 400 kV substation of Red Eléctrica de España.

When was the favorable Environmental Impact Statement issued for this project?

The favorable Environmental Impact Statement (EIA) was issued on 28 August 2026. It imposes preventive, corrective and compensatory measures that are mandatory for the promoter during construction and operation of the installation.

Official source

View complete regulation at official source

Notice: This article is for informational purposes only and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-23982



Share:
E
Equipo Editorial CambiosLegales