Summary
The CNMC sets at €143.5 million the remunerable investment of the submarine electrical link connecting Tenerife with La Gomera, already in service since late 2025.
Detailed analysis
PRO
The CNMC modifies the singularity parameters of the 66 kV submarine link between the Chío (Tenerife) and El Palmar (La Gomera) substations, operated by Red Eléctrica, and includes the installation in the special remuneration regime for singular investments. A remunerable investment of €143.527 million is set, with a ma…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 26 de junio de 2026, de la Comisión Nacional de los Mercados y la Competencia, sobre la modificación de parámetros de la resolución por la que se otorga el carácter singular del enlace subterráneo-submarino de 66 kV entre las subestaciones eléctricas de Chío (Tenerife) y El Palmar (La Gomera) y su inclusión en el régimen retributivo de inversiones singulares con características técnicas especiales.
Planta Solar OPDE 25 is authorized to build a 43.9 MW battery storage system alongside its Covatillas 3 photovoltaic park in Castillejo de Iniesta (Cuenca). The...
Promoting company Planta Solar OPDE 25 SL and renewable energy sector in Cuenca
Arena Power Solar 33 renounces construction of a 54 MW solar plant in Beas and Trigueros (Huelva) due to incompatibility with the future Seville-Huelva high-spe...
Promoter company Arena Power Solar 33 SLU and municipalities of Beas and Trigueros (Huelva)
Arena Power Solar 35 renounces construction of a 57.5 MW solar plant in Huelva as it interferes with the future Seville-Huelva high-speed rail route. The Direct...
Renewable energy developers and photovoltaic sector companies in Huelva
Savanna Power Solar 9 withdraws from building a 59 MW solar plant in Huelva due to incompatibility with the future AVE Sevilla-Huelva. The Ministry accepts the ...
Renewable energy developers and photovoltaic sector in Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia