Environmental approval of the offshore wind energy research platform off Roses (Girona)
08 Jul 2026Effective: 08 Jul 2026123 views
Who is affected:
IREC promoter, marine energy sector, fishermen and municipalities of Alt Empordà (Girona)
Summary
The Government approves the environmental impact of PLEMCAT, a 30 MW platform to test floating wind turbines at sea off Roses bay. It is the first step to build this marine energy research infrastructure in Catalonia.
Detailed analysis
PRO
The General Directorate of Quality and Environmental Assessment issues a favorable environmental impact statement for the PLEMCAT project, promoted by IREC, which includes up to three floating wind turbines of up to 15 MW each in an area of 7.82 km² located 24 km from the Girona coast. The infrastructure includes a hub…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 22 de junio de 2026, de la Dirección General de Calidad y Evaluación Ambiental, por la que se formula declaración de impacto ambiental del proyecto «Plataforma de investigación en energías marinas de Cataluña-PLEMCAT, de 30 MW, y su infraestructura de evacuación, frente a la costa de la bahía de Roses, en la provincia de Girona».
The European Commission approves a provisional agreement with the United Kingdom on Gibraltar in the field of atomic energy. The agreement regulates nuclear coo...
Nuclear operators, regulatory authorities and companies with activities in Gibraltar or linked to the territory
The CNMC calculates the pending balance of the regulatory account of the technical manager of the gas system at the end of 2025, validating costs of 1.8 million...
Technical manager of the gas system (Enagás GTS) and natural gas system users
The Basque Country renews for 5 years the permit to install in the national electrical grid the measurement transformers manufactured by Arteche Hermanos in Mun...
Electrotécnica Arteche Hermanos SL and electrical grid operators using their transformers
The CNMC sets at €143.5 million the remunerable investment of the submarine electrical link connecting Tenerife with La Gomera, already in service since late 20...
Red Eléctrica de España and electricity consumers of the Canary Islands system (Tenerife and La Gomera)
The list of industrial sectors receiving compensation for indirect CO2 costs in electricity is expanded and the aid calculation parameters are updated through 2...
Energy-intensive industries exposed to carbon leakage: chemicals, aluminium, steel and similar sectors
Material errors are corrected in the resolution that accepted Acciona's withdrawal to build a 43 MWp photovoltaic plant in Ayora (Valencia). The change affects ...
Corporación Acciona Eólica, SL and state energy administration