Authorization Denied for Installing Solar Panels Next to Iberdrola's Radona II Wind Farm in Soria
06 Aug 2026Effective: 06 Aug 202632 views
Who is affected:
Iberdrola Renovables Castilla y León and renewable energy project developers in Spain
Summary
The Ministry denies Iberdrola permission to build a 32 MW photovoltaic module in Soria for failing to provide required documentation. The company did not meet environmental and administrative requirements after several requests for compliance.
Detailed analysis
PRO
The General Directorate of Energy Policy and Mines rejects Iberdrola Renovables Castilla y León's application to build the Radona II photovoltaic module (32.655 MW) in Taroda and Alcubilla de las Peñas (Soria), intended to be hybridized with the existing homonymous wind farm. The denial occurs after multiple requests f…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 8 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Iberdrola Renovables Castilla y León, SA, de autorización administrativa de construcción y declaración, en concreto, de utilidad pública del módulo de generación fotovoltaica Radona II, de 32,655 MW de potencia instalada, y sus infraestructuras para evacuación de energía eléctrica, para su hibridación con el parque eólico existente Radona II, de 32 MW de potencia instalada, en Taroda y Alcubilla de las Peñas (Soria).
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection
Naturgy Renovables withdraws its application to build a 39 MW photovoltaic plant and 20 MW battery in Valladolid. The Ministry accepts the withdrawal and closes...
Naturgy Renovables SLU and photovoltaic project developers in state processing