Authorization Denied for Umiko 46.5 MW Solar Park in Tauste (Zaragoza)
16 Sep 2026Effective: 16 Sep 20263 views
Who is affected:
Promoters of photovoltaic parks and renewable energy sector companies
Summary
The Ministry denies authorization for the Umiko solar park in Zaragoza due to expiration of grid access permits. The promoting company ultimately requested the filing of the case.
Detailed analysis
PRO
The General Directorate of Energy Policy and Mines dismisses the request for prior administrative authorization of the Umiko photovoltaic park (46.5 MW) in Tauste, Zaragoza, promoted by Energía Inagotable de Umiko, SL. The main reason is the expiration of access and connection permits to the transmission grid at the Ju…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 31 de agosto de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Energía Inagotable de Umiko, SL, de autorización administrativa previa del parque solar fotovoltaico “Umiko”, de 46,5 MW de potencia instalada, en Tauste (Zaragoza).
The Ministry authorizes Red Eléctrica to install a 250 MVA synchronous compensator at the 400 kV substation in Cabra (Córdoba) to strengthen the national electr...
Red Eléctrica de España and the national electrical system; municipalities of Cabra and Lucena (Córdoba)
Red Eléctrica de España obtains permission to build a 400 kV overhead line in Sagunto. The project includes mandatory environmental measures and has been declar...
Red Eléctrica de España, owners of affected land and municipality of Sagunto (Valencia)
An error in the authorization of the Elawan Olmedo I photovoltaic plant in Valladolid is corrected, adjusting its official power from 50,064 MW to 49,61 MW.
Elawan Energy Olmedo 1, SL, and administrations with competencies over the installation
The European Commission extends surveillance over imports of renewable ethanol for fuel. It allows monitoring of trade flows and detection of possible market di...
Renewable ethanol importers, biofuel operators and EU energy sector
The Ministry authorizes the construction of a 133.5 MW photovoltaic park in Cádiz, including a substation and evacuation line. The installation was declared of ...
Developer Fénix Renovable SL, owners of affected land and municipalities of Puerto Real and Jerez de la Frontera
Numbering errors are corrected in the resolution that accepted the withdrawal of the Taraguilla wind farm of 62.7 MW in Cádiz. It only affects the internal numb...
Desarrollos Renovables Eólicos y Solares, SLU, and related administrative records