Bierzo Wind II 9 MW wind farm in León cancelled following unfavorable environmental impact
05 Nov 2026Effective: 01 Jun 20260 views
Who is affected:
Renewable energy developers and wind sector in environmentally sensitive areas
Summary
Ekain Renovables withdraws from constructing the Bierzo Wind II wind farm in León after receiving an unfavorable environmental impact declaration and losing grid connection permits.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines accepts the withdrawal of Ekain Renovables, SL, for the Bierzo Wind II wind farm of 9 MW in the León municipalities of Encinedo and Benuza. The project was blocked primarily by an unfavorable environmental impact declaration issued in March 2026, which warned of signi…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 1 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se acepta el desistimiento formulado por Ekain Renovables, SL, de la solicitud de autorización administrativa previa y autorización administrativa de construcción del parque eólico «Bierzo Wind II», de 9 MW de potencia instalada, y de su infraestructura de evacuación, en la provincia de León.
The Ministry denies authorization for the 'As Fenteiras' wind farm in Pontevedra following an unfavorable environmental impact assessment. Grid connection permi...
Promoters of wind farms and renewable projects exceeding 50 MW in Spain
A material error in the authorization of Iberdrola's 60 MW Azután III solar plant in Toledo is corrected, removing an incorrect reference to an unauthorized mod...
Iberdrola Generación SAU and local administrations of Calera y Chozas and Alcolea de Tajo (Toledo)
A material error in the authorization of the Azután I solar plant (60 MW) by Iberdrola in Toledo is corrected, removing an incorrect reference to an unauthorize...
Iberdrola Generación SAU and administrations involved in the Azután I solar project in Toledo
Ekain Renovables withdraws from building the Bierzo Wind I wind farm in León and Ourense after obtaining an unfavorable environmental impact statement and losin...
Ekain Renovables, SL and wind energy sector in León and Ourense
The Ministry environmentally approves five wind farms in Lugo, Pontevedra and Ourense. Following modifications, the final project reduces wind turbines to minim...
Wind farm developers, affected Galician municipalities, renewable energy sector and REE
The CNMC approves the final values of incentives or penalties to Red Eléctrica for its performance as electricity system operator in 2025. This adjusts its remu...
Electricity system operator (Red Eléctrica) and, indirectly, electricity consumers