Summary
A material error in the authorization of the Azután I solar plant (60 MW) by Iberdrola in Toledo is corrected, removing an incorrect reference to an unauthorized project. The content and scope of the authorization remain unchanged.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines rectifies a material error in the July 2025 resolution that authorized Iberdrola Generación the installation of the Azután I photovoltaic solar facility of 60 MW in Toledo. The error consisted of including a reference to the 'Refunded Hybrid Installation Project Azutá…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 18 de octubre de 2026, de la Dirección General de Política Energética y Minas, por la que corrigen errores en la de 18 de julio de 2025, por la que se otorga a Iberdrola Generación, SAU, autorización administrativa previa de la instalación solar fotovoltaica «Azután I», de 60 MW de potencia instalada, y su infraestructura de evacuación, para hibridación del grupo 1 de la central hidráulica existente Azután, en Calera y Chozas y Alcolea de Tajo (Toledo).
The CNMC reduces the regulated remuneration of electricity companies that use their fiber optics for activities other than transport and distribution. The adjus...
Electricity transport and distribution companies with fiber optics in regulated networks
A material error in the authorization of Iberdrola's 60 MW Azután III solar plant in Toledo is corrected, removing an incorrect reference to an unauthorized mod...
Iberdrola Generación SAU and local administrations of Calera y Chozas and Alcolea de Tajo (Toledo)
The Ministry denies authorization for the 'As Fenteiras' wind farm in Pontevedra following an unfavorable environmental impact assessment. Grid connection permi...
Promoters of wind farms and renewable projects exceeding 50 MW in Spain
Ekain Renovables withdraws from constructing the Bierzo Wind II wind farm in León after receiving an unfavorable environmental impact declaration and losing gri...
Renewable energy developers and wind sector in environmentally sensitive areas
Ekain Renovables withdraws from building the Bierzo Wind I wind farm in León and Ourense after obtaining an unfavorable environmental impact statement and losin...
Ekain Renovables, SL and wind energy sector in León and Ourense
The Ministry environmentally approves five wind farms in Lugo, Pontevedra and Ourense. Following modifications, the final project reduces wind turbines to minim...
Wind farm developers, affected Galician municipalities, renewable energy sector and REE