Authorization to add 22 MW battery storage system to solar plant in Talayuela (Cáceres)
01 Jul 2026Effective: 01 Jul 2026127 views
Who is affected:
Oropesa Solar SL and renewable energy sector in Extremadura
Summary
Oropesa Solar is authorized to add a 22.26 MW battery system to its existing photovoltaic plant in Talayuela, creating a hybrid installation with 66.81 MW total capacity.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Oropesa Solar, SL prior authorization and construction permit for the BESS Talayuela II storage module of 22.26 MW, which will be hybridized with the existing photovoltaic plant of 44.55 MW. The resulting installation will have 66.81 MW of total power and will …
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 17 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Oropesa Solar, SL, autorización administrativa previa y autorización administrativa de construcción para el módulo de almacenamiento «Talayuela II BESS», de 22,26 MW de potencia instalada, y parte de su infraestructura de evacuación, para su hibridación con la planta fotovoltaica existente, «PSFV Talayuela II», de 44,55 MW de potencia instalada, conformando una instalación hibrida de 66,81 MW de potencia instalada, en Talayuela (Cáceres).
Material errors are corrected in the resolution that accepted Acciona's withdrawal from building a 45 MW photovoltaic plant in Ayora (Valencia). The correction ...
Corporación Acciona Eólica, SL, and the Dirección General de Política Energética y Minas
The auction procedure is regulated so that high-efficiency cogeneration facilities obtain economic aid from the State. It affects industrial plants that produce...
Remuneration values for operation in the third quarter of 2026 are updated for renewable electrical installations, cogeneration and waste whose costs depend on ...
Holders of renewable electrical installations, cogeneration and waste with specific remuneration regime
Arena Power Ren 29 is authorized to operate a 66 MW battery system in Tarifa with its electrical evacuation infrastructure. The project passed the simplified en...
Developer company Arena Power Ren 29 SL and operators with shared evacuation infrastructure in Tarifa
Errors are corrected in the resolution that declared the 154 MW photovoltaic plant in Valencian municipalities as a matter of public utility. The correction cla...
Iberenova Promociones SAU and landowners in the affected municipalities of Valencia
AECID and CNMC will collaborate to train Latin American regulators in energy transition and digital transformation. Activities will be conducted in 2026 and 202...
AECID, CNMC and public energy and telecommunications regulators in Latin America