Authorization to add 22 MW battery storage system to solar plant in Talayuela (Cáceres)
01 Jul 2026Effective: 01 Jul 2026105 views
Who is affected:
Oropesa Solar SL and renewable energy sector in Extremadura
Summary
Oropesa Solar is authorized to add a 22.26 MW battery system to its existing photovoltaic plant in Talayuela, creating a hybrid installation with 66.81 MW total capacity.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Oropesa Solar, SL prior authorization and construction permit for the BESS Talayuela II storage module of 22.26 MW, which will be hybridized with the existing photovoltaic plant of 44.55 MW. The resulting installation will have 66.81 MW of total power and will …
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 17 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Oropesa Solar, SL, autorización administrativa previa y autorización administrativa de construcción para el módulo de almacenamiento «Talayuela II BESS», de 22,26 MW de potencia instalada, y parte de su infraestructura de evacuación, para su hibridación con la planta fotovoltaica existente, «PSFV Talayuela II», de 44,55 MW de potencia instalada, conformando una instalación hibrida de 66,81 MW de potencia instalada, en Talayuela (Cáceres).
The remuneration values for operation in the fourth quarter of 2026 are updated for renewable electrical installations, cogeneration and waste whose costs depen...
Holders of renewable, cogeneration and waste installations with specific remuneration regime
Navarre extends the suspension of new biomethane plant projects managing external waste until December 31, 2028, while developing specific regulations.
Biomethane plant developers in Navarre and Navarrese agri-livestock sector
The CNMC approves the final review of gas losses (shrinkage) in plants, transport and distribution networks for the 2024 gas year, adjusting the remuneration of...
Holders of regasification plants, natural gas transport and distribution networks
The CNMC calculates the additional costs recognized to REE as the electricity system operator in 2025. The resulting balance will be incorporated into the follo...
Red Eléctrica de España (REE) as the electricity system operator and electricity market agents
The EU Council approves the European position to modify gas transport tariff rules in the EEA. It affects how tolls on gas networks are calculated and harmonize...
Gas transport network operators and traders in the EEA