Authorization of 28 MW storage battery system to hybridize with solar plant in Utrera (Seville)
25 Aug 2026122 views
Who is affected:
Renewable energy sector companies, solar plant developers and grid operators
Summary
The Ministry authorizes Bianor Solar to build a 28.37 MW battery storage system alongside its existing photovoltaic plant in Utrera. The installation will improve energy storage capacity and renewable energy management on the electrical grid.
Detailed analysis
PRO
The General Directorate of Energy Policy and Mines grants Bianor Solar, SLU, prior authorization and construction permit for a 28.37 MW battery storage module in Utrera (Seville), to be hybridized with its existing 33 MW photovoltaic park. The processing was conducted under the simplified procedure of RD 997/2025, whic…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 31 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Bianor Solar, SLU, autorización administrativa previa y autorización administrativa de construcción del módulo de almacenamiento por baterías «Bianor», de 28,37 MW de potencia instalada, y para su infraestructura de evacuación, para su hibridación con el parque solar fotovoltaico existente «Bianor», de 33 MW de potencia instalada, en Utrera (Sevilla).
The Ministry denies authorization for the Satrebares wind farm due to an unfavorable environmental impact declaration and expiration of grid connection permits.
Promoters of wind farms and renewable energy projects in Spain
An error in the authorization of the Elawan Olmedo III photovoltaic plant in Valladolid is corrected, adjusting its installed capacity from 50.064 MW to 49.61 M...
Elawan Energy Olmedo 3 SL and administrations managing access to the electrical grid
Technical errors in the European regulation establishing measures to reduce gas consumption are corrected. It affects the energy-saving regulations currently in...
Gas-consuming companies, EU Member States and energy operators
Savanna Power Solar 10 withdraws from building a 60 MW photovoltaic plant in Trigueros (Huelva) as it interferes with the future Seville-Huelva high-speed rail ...
Renewable energy developers and photovoltaic sector in Huelva
The Ministry authorizes Naturgy Vento to build a 49.35 MW photovoltaic plant in El Bonillo (Albacete) that will share infrastructure with an already existing wi...
Naturgy Vento SAU, local and regional administrations of Albacete and Castilla-La Mancha