Authorization of 20 MW storage battery system to hybridize with solar plant in Alcázar de San Juan
14 Oct 2026Effective: 14 Oct 202649 views
Who is affected:
Ictio Solar Berenice SL and energy operators in the Alcázar de San Juan area
Summary
Ictio Solar Berenice is authorized to install a battery system of almost 20 MW alongside its existing photovoltaic plant in Ciudad Real, forming a combined installation of 67 MW.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants prior administrative authorization to Ictio Solar Berenice, SL for a 19.96 MW battery storage module in Alcázar de San Juan (Ciudad Real), which will be hybridized with the existing FV Ictio Alcázar III photovoltaic plant of 47.19 MW, resulting in a total insta…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 7 de septiembre de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Ictio Solar Berenice, SL, la autorización administrativa previa para el módulo de almacenamiento por baterías «ALM Ictio Alcázar III», de 19,96 MW de potencia instalada, y su infraestructura de evacuación, para su hibridación con la planta fotovoltaica existente, «FV Ictio Alcázar III», de 47,19 MW de potencia instalada, conformando una instalación de 67,15 MW de potencia instalada, en Alcázar de San Juan (Ciudad Real).
The European Commission validates the RSB EU RED scheme to accredit the sustainability of biofuels and renewable fuels. It replaces the previous certification f...
Producers, importers and distributors of biofuels and renewable fuels in the EU
The environmental impact statement is approved for three wind farms that will be hybridized with existing solar plants in Belinchón and Zarza de Tajo (Cuenca), ...
Promoters Elawan Fotovoltaica Belinchón 1, 2 and 3 SL; municipalities of Belinchón and Zarza de Tajo
Ictio Solar Auriga is authorized to install a 19.96 MW battery system alongside its existing solar plant in Ciudad Real, forming a hybrid installation of 67 MW.
Ictio Solar Auriga SL and renewable energy sector in Castilla-La Mancha
Technical corrections to the European RED III Directive promoting renewable energy are published. It affects regulations on fuels and renewable energy targets i...
Energy companies, renewable energy developers, biofuel producers, and public administrations