Environmental approval of a 199.8 MW solar plant in the Community of Madrid
02 May 2026Effective: 16 Apr 2026151 views
Who is affected:
Photovoltaic project promoters, renewable energy sector and Madrid administrations
Summary
The environmental impact declaration of the FV Caiba photovoltaic plant in Madrid is approved, with 199.8 MW of power. The project includes its electrical evacuation infrastructure.
Detailed analysis
PRO
The Directorate General for Quality and Environmental Assessment issues a favorable environmental impact declaration for the FV Caiba photovoltaic plant, with 199.8 MW of installed capacity in the Community of Madrid. This resolution is a key step for the project to obtain the necessary administrative authorizations an…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 16 de abril de 2026, de la Dirección General de Calidad y Evaluación Ambiental, por la que se formula declaración de impacto ambiental del proyecto «Planta fotovoltaica FV Caiba, de 199,8 MW de potencia instalada, y su infraestructura de evacuación, en la Comunidad de Madrid».
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection
Naturgy Renovables withdraws its application to build a 39 MW photovoltaic plant and 20 MW battery in Valladolid. The Ministry accepts the withdrawal and closes...