Energy BOE Importance: 5/10

Enel Green Power reduces commitments in Mudéjar renewable park (Teruel) following environmental assessment

03 Nov 2026 Effective: 03 Nov 2026 4 views
Who is affected:
Enel Green Power España, administrations of Teruel and Zaragoza, renewable sector

Summary

The environmental impact declaration requires reducing the Mudéjar renewable project power from 1,844 MW to 406 MW. Employment and local investment commitments are adjusted proportionally.

Detailed analysis PRO

The Order modifies the 2022 award by which Enel Green Power España obtained 1,202 MW of access capacity at the Mudéjar 400 kV node. The EIA of February 2026 was unfavorable for one of the seven facilities and conditioned the rest, forcing a reduction in installed capacity from 1,844 MW to 406.3 MW and access capacity t…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Orden TED/1157/2026, de 19 de octubre, por la que se modifica la Orden TED/1146/2022, de 21 de noviembre, por la que se resuelve el concurso público para la concesión de capacidad de acceso de evacuación a la red de transporte de energía eléctrica de instalaciones de generación de procedencia renovable en el nudo de transición justa Mudéjar 400 KV, convocado mediante Orden TED/1182/2021, de 2 de noviembre.