Authorization Denied for Carina Solar 10 Solar Plant of 49.4 MW in Toledo and Madrid
13 Aug 2026Effective: 13 Aug 202639 views
Who is affected:
Solaria Promoción y Desarrollo Fotovoltaico SLU and renewable energy developers
Summary
The Directorate General for Energy Policy denies Solaria the authorization to build a 49.4 MW photovoltaic plant in Toledo and Madrid. The main reason is the expiration of grid access and connection permits.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines dismisses Solaria's application for the Carina Solar 10 photovoltaic plant (49.4 MW) in municipalities of Toledo and Madrid. The project, initiated in 2020, had passed favorable environmental impact assessment in 2023 and obtained prior administrative authorization in…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 20 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Solaria Promoción y Desarrollo Fotovoltaico, SLU, de autorización administrativa previa y autorización administrativa de construcción para la instalación fotovoltaica Carina Solar 10, de 49,4 MW de potencia instalada, y su infraestructura de evacuación, en las provincias de Toledo y Madrid.
Planta Solar OPDE 25 is authorized to build a 43.9 MW battery storage system alongside its Covatillas 3 photovoltaic park in Castillejo de Iniesta (Cuenca). The...
Promoting company Planta Solar OPDE 25 SL and renewable energy sector in Cuenca
Arena Power Solar 33 renounces construction of a 54 MW solar plant in Beas and Trigueros (Huelva) due to incompatibility with the future Seville-Huelva high-spe...
Promoter company Arena Power Solar 33 SLU and municipalities of Beas and Trigueros (Huelva)
Arena Power Solar 35 renounces construction of a 57.5 MW solar plant in Huelva as it interferes with the future Seville-Huelva high-speed rail route. The Direct...
Renewable energy developers and photovoltaic sector companies in Huelva
Savanna Power Solar 9 withdraws from building a 59 MW solar plant in Huelva due to incompatibility with the future AVE Sevilla-Huelva. The Ministry accepts the ...
Renewable energy developers and photovoltaic sector in Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia