Summary
The Ministry denies the 80 MW photovoltaic project in Almogía (Málaga) due to lack of valid environmental assessment and expiration of grid connection permits.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines dismisses the application by VE Sonnedix SPV Gamma, SLU to build the Aliaga Solar II solar park (80 MWp) in Almogía, Málaga. The denial is based on two main grounds: the termination of the environmental impact assessment procedure due to insufficient documentation, ar…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 25 de septiembre de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de VE Sonnedix SPV Gamma, SLU, de autorización administrativa previa, autorización administrativa de construcción y declaración, en concreto, de utilidad pública, del parque solar fotovoltaico Aliaga Solar II, de 80 MWp, y de su infraestructura de evacuación asociada, en la provincia de Málaga.
The Government sets minimum services in the hydrocarbon sector for the general strike on November 11, 2026. At least 20% of gas stations per region must remain ...
Workers and companies in the hydrocarbon sector, gas stations and gas distribution
The Government sets minimum services to guarantee electricity supply during the general strike on November 11, 2026 called by CGT, CCOO, UGT and other unions.
Workers and companies in the electricity sector: generation, transmission and distribution
The Ministry approves the environmental impact of a 72 MWh battery system in Cañada Vellida (Teruel) to hybridize with the existing solar plant. The project inc...
Promoter Planta Solar OPDE 7 SL, Aragón administrations and municipalities of Cañada Vellida and Mezquita de Jarque
Energy savings certificates (CAE) obtained by replacing gas boilers with heat pumps in residential buildings are multiplied, with higher bonuses for vulnerable ...
Property owners, property owner associations, installers and energy service companies
The CNMC reduces the regulated remuneration of electricity companies that use their fiber optics for activities other than transport and distribution. The adjus...
Electricity transport and distribution companies with fiber optics in regulated networks
A material error in the authorization of the Azután I solar plant (60 MW) by Iberdrola in Toledo is corrected, removing an incorrect reference to an unauthorize...
Iberdrola Generación SAU and administrations involved in the Azután I solar project in Toledo