Authorization for Enel hybrid solar and wind plant in Teruel with over 107 MW of power
25 Jun 2026Effective: 25 Jun 202646 views
Who is affected:
Enel Green Power España, municipalities of Alcorisa, Calanda and Alcañiz, and renewable energy developers in the surrounding area
Summary
Enel Green Power España is authorized to build a hybrid photovoltaic and wind installation in Alcorisa, Calanda and Alcañiz (Teruel) with 107 MW of total power. It includes substations and evacuation lines at 400 kV.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants prior administrative authorization to Enel Green Power España for the HB7-Pitarra hybrid installation in Teruel, composed of 61.729 MW photovoltaic and 45.6 MW wind. The evacuation infrastructure includes two collector substations and aerial lines at 400 kV con…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 1 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Enel Green Power España, SL, autorización administrativa previa para la instalación híbrida «HB7-Pitarra», compuesta por el módulo solar fotovoltaico «Regallo», de 61,729 MW de potencia instalada, el módulo eólico «Pitarra», de 45,6 MW de potencia instalada, y sus infraestructuras de evacuación, en Alcorisa, Calanda y Alcañiz (Teruel).
La empresa Savanna Power Solar 9 renuncia a construir una planta solar de 59 MW en Huelva por incompatibilidad con el futuro AVE Sevilla-Huelva. El Ministerio a...
Promotores de energías renovables y sector fotovoltaico en Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection