Authorization for new 400 kV electrical substation in Carreño (Asturias)
30 Mar 2026Effective: 10 Mar 2026204 views
Who is affected:
Landowners of affected plots and energy companies in Asturias
Summary
Red Eléctrica de España is authorized to build a new electrical substation in Carreño, Asturias. The installation is declared of public utility.
Detailed analysis
PRO
The Dirección General de Política Energética y Minas grants Red Eléctrica de España, SAU, prior administrative and construction authorization for the Cardoso 400 kV substation in Carreño (Asturias), including three new bays and interconnection of autotransformer ATP1. The public utility declaration facilitates compulso…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 10 de marzo de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Red Eléctrica de España, SAU, autorización administrativa previa y autorización administrativa de construcción para la nueva subestación Cardoso 400 kV, con tres nuevas posiciones, y la interconexión del autotransformador ATP1, en Carreño (Asturias), y se declara, en concreto, la utilidad pública.
Red Eléctrica de España is authorized to build a new high-voltage substation in Sevilla and expand the one in Carmona to strengthen the electricity grid.
Affected landowners, energy sector and industrial companies in Sevilla
Remuneration values for operation are updated for Q2 2026 for electricity installations whose costs depend on fuel prices. It affects the economic compensation ...
Owners of electricity generation installations with costs dependent on fuel prices
Red Eléctrica de España is authorized to build a 400 kV overhead line between the Grado and Cardoso substations in Carreño, Asturias. The project is declared of...
Red Eléctrica de España, landowners along the route in Carreño (Asturias)
The environmental impact report is approved to modernise a 400 kV power line between Lleida and Zaragoza. The project aims to improve electricity transmission c...
Energy companies, construction firms and landowners in Lleida and Zaragoza
The DGRN requires registration of leases over part of a property for photovoltaic installations even when the exact georeferencing of the leased portion is not ...
Photovoltaic plant developers, rural property owners and land registrars