Authorization to close and dismantle the high-voltage power line Morella-La Plana in Castellón
22 Jun 2026Effective: 22 Jun 202649 views
Who is affected:
Red Eléctrica de España, SAU, and municipalities in Castellón affected by the route
Summary
Red Eléctrica de España is authorized to close and dismantle the 400 kV power line between Morella and La Plana in Castellón, 65 km long, to replace it with a new double-circuit line.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Red Eléctrica de España, SAU, authorization to close and dismantle the 400 kV single-circuit overhead line Morella-La Plana, 65.2 km long, in the province of Castellón. The project is included in the Transmission Network Development Plan 2021-2026 and is a prer…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 3 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Red Eléctrica de España, SAU, autorización de cierre para la línea aérea de transporte de energía eléctrica a 400 kV, simple circuito, Morella-La Plana, en la provincia de Castellón.
La empresa Savanna Power Solar 9 renuncia a construir una planta solar de 59 MW en Huelva por incompatibilidad con el futuro AVE Sevilla-Huelva. El Ministerio a...
Promotores de energías renovables y sector fotovoltaico en Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection