Energy BOE Importance: 3/10

Authorization to add 21.69 MW battery storage system to FV Aspe solar plant in Altarejos (Cuenca)

15 Aug 2026 37 views
Who is affected:
GR Aspe Renovables SLU and renewable energy sector in Cuenca

Summary

The Ministry authorizes GR Aspe Renovables to expand its solar plant in Cuenca with a 21.69 MW battery storage system, creating a hybrid installation of 50 MW total.

Detailed analysis PRO

The Directorate General for Energy Policy and Mines grants prior authorization and construction permit to GR Aspe Renovables to hybridize its existing 49.11 MW photovoltaic plant with a 21.69 MW battery storage module in Altarejos (Cuenca). The resulting installation will have 50 MW of installed capacity and will inclu…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 20 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a GR Aspe Renovables, SLU, autorización administrativa previa y autorización administrativa de construcción para el módulo de almacenamiento Aspe, de 21,69 MW, y su infraestructura de evacuación, para su hibridación con la instalación solar fotovoltaica existente «FV Aspe», de 49,11 MW de potencia instalada, que conforman una instalación híbrida de 50 MW de potencia instalada, en Altarejos (Cuenca).