Authorization of new high-voltage power line between Mezquita de Jarque and Teruel
07 Aug 2026Effective: 07 Aug 202642 views
Who is affected:
Red Eléctrica de España, municipalities in Teruel affected and landowners along the route
Summary
Authorization is granted to build a 400 kV aerial line of approximately 58 km between two substations in Teruel. The work is declared of public utility, which allows land expropriation if necessary.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Red Eléctrica de España administrative authorization for construction and declares the public utility of a double-circuit aerial line at 400 kV of approximately 57.8 km in the province of Teruel. The installation is part of the Transport Network Development Pla…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 16 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Red Eléctrica de España, SAU, autorización administrativa de construcción para el proyecto de construcción de la línea aérea de transporte de energía eléctrica, de doble circuito a 400 kV, entre la subestación Mezquita 400 kV, en el término municipal de Mezquita de Jarque, y la subestación Platea 400 kV, en Teruel (Teruel), y se declara, en concreto, la utilidad pública.
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection
Naturgy Renovables withdraws its application to build a 39 MW photovoltaic plant and 20 MW battery in Valladolid. The Ministry accepts the withdrawal and closes...
Naturgy Renovables SLU and photovoltaic project developers in state processing