Environmental approval of Repsol self-consumption solar plant in Puertollano (Ciudad Real)
20 Jun 2026Effective: 20 Jun 202652 views
Who is affected:
Repsol Petróleo SA as promoter; energy industrial sector in Puertollano
Summary
The Directorate General for Environmental Quality approves the environmental impact report of a 48 MW photovoltaic plant by Repsol in Puertollano for industrial self-consumption, hybridized with its existing cogeneration.
Detailed analysis
PRO
The resolution formulates the simplified environmental impact report of the Repsol Petróleo photovoltaic project in Puertollano, with 48.02 MW of solar generation and 4 MW of LFP battery storage, to be hybridized with the existing thermoelectric cogeneration of 80.5 MW. The installation occupies 93.73 hectares fenced w…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 9 de junio de 2026, de la Dirección General de Calidad y Evaluación Ambiental, por la que se formula informe de impacto ambiental del proyecto «Instalación fotovoltaica "Autoconsumo Puertollano Refino" y el módulo de almacenamiento, para su hibridación con la instalación de cogeneración termoeléctrica, y su infraestructura de evacuación, en Ciudad Real».
Planta Solar OPDE 25 is authorized to build a 43.9 MW battery storage system alongside its Covatillas 3 photovoltaic park in Castillejo de Iniesta (Cuenca). The...
Promoting company Planta Solar OPDE 25 SL and renewable energy sector in Cuenca
Arena Power Solar 33 renounces construction of a 54 MW solar plant in Beas and Trigueros (Huelva) due to incompatibility with the future Seville-Huelva high-spe...
Promoter company Arena Power Solar 33 SLU and municipalities of Beas and Trigueros (Huelva)
Arena Power Solar 35 renounces construction of a 57.5 MW solar plant in Huelva as it interferes with the future Seville-Huelva high-speed rail route. The Direct...
Renewable energy developers and photovoltaic sector companies in Huelva
Savanna Power Solar 9 withdraws from building a 59 MW solar plant in Huelva due to incompatibility with the future AVE Sevilla-Huelva. The Ministry accepts the ...
Renewable energy developers and photovoltaic sector in Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia