Allocation of 408 MW of renewable evacuation capacity at the Meirama electrical node to Coventina Renovables
09 Jun 2026Effective: 09 Jun 2026131 views
Who is affected:
Renewable energy development companies and electrical system operators in just transition areas
Summary
The Ministry allocates to Coventina Renovables the access capacity of 408 MW at the just transition node Meirama 220 kV for renewable generation. The company provided a guarantee of 52.8 million euros.
Detailed analysis
PRO
Order TED/578/2026 resolves the public tender called in December 2024 to assign 408 MW of evacuation capacity at the Meirama 220 kV node, located in a just transition area in Galicia. Of seven admitted applications, Coventina Renovables obtained the highest score (73.53 points) with its CHR Meirama project, surpassing …
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Orden TED/578/2026, de 29 de mayo, por la que se resuelve el concurso público para la concesión de capacidad de acceso de evacuación a la red de energía eléctrica de instalaciones de generación de electricidad de procedencia renovable en el nudo de transición justa Meirama 220 kV.
Enresa is authorized to build a temporary storage facility for radioactive waste from the Vandellós I nuclear power plant, now decommissioned. The facility will...
Enresa, Nuclear Safety Council, local administrations and citizens in the Vandellós area
Falck Renewables Power 3 withdraws from constructing a 121.5 MW solar park in Velilla de San Antonio and Loeches (Madrid) after receiving an unfavorable environ...
Renewable energy developers, photovoltaic investors and municipalities of Velilla de San Antonio and Loeches
The Ministry denies Energías Renovables Yadisema SL authorization to build a 63.83 MW solar plant in Toledo due to expiration of grid access and connection perm...
Promoters of photovoltaic and renewable installations processing authorizations in Spain
Corporación Acciona Eólica withdraws from its 43 MW hybrid photovoltaic plant project in Ayora, Valencia. The Ministry formally accepts the abandonment of the a...
Corporación Acciona Eólica, SL and administrations of Valencia and Albacete
Corporación Acciona Eólica withdraws from its 42 MW hybrid photovoltaic plant project in Ayora, Valencia. The Ministry officially accepts the abandonment of the...
Corporación Acciona Eólica, SL and administrations of Valencia and Albacete
The Ministry authorizes Red Eléctrica to install a 400/220 kV transformer of 600 MVA in Soria to connect two substations. The work is included in the Electricit...
Red Eléctrica de España, SAU, and administrations of Castilla y León involved in the area