Key data
| Regulation | Resolution of October 22, 2026, from the General Directorate of Energy Policy and Mines |
|---|---|
| BOE Publication | November 16, 2026 |
| Effective date | November 16, 2026 |
| Affected project | Rojalinda photovoltaic plant, 70.8 MW |
| Developer | Energía, Innovación y Desarrollo Fotovoltaico, SA |
| Location | Municipalities in the provinces of Murcia and Alicante |
| Connection substation | Rojales 220 kV |
| File start date | 2021 |
| Category | Energy / Renewables |
A 70.8 MW project that had been in process since 2021 has just been definitively closed. The General Directorate of Energy Policy and Mines has rejected the request for prior administrative authorization of the Rojalinda photovoltaic plant, promoted by Energía, Innovación y Desarrollo Fotovoltaico, SA, in municipalities in the provinces of Murcia and Alicante. The resolution, published in the BOE on November 16, 2026, leaves no room for interpretation: the file is closed without possibility of correction.
What is relevant for the sector is not just this specific project. It is the combination of two grounds for denial that, separately, are already fatal for any photovoltaic authorization. Together, they make any practical appeal unfeasible.
What does this resolution establish?
The resolution rejects the request for prior administrative authorization of the Rojalinda solar park for two independent and cumulative reasons:
- Unfavorable environmental impact declaration (DIA): issued on April 24, 2026, concludes that the project would cause significant negative impacts on the environment without sufficient possibility of correction. An unfavorable DIA is, by itself, sufficient grounds to deny authorization.
- Expiration of grid access and connection permits: the permits to connect to the Rojales 220 kV substation expired in February 2024. Without valid grid permits, it is not possible to obtain prior administrative authorization, regardless of the environmental outcome.
Additionally, the developer did not submit comments during the public hearing procedure, which deprived the file of any defense argument that could have qualified the resolution. The file, initiated in 2021, is definitively closed.
Economic and operational impact
For the developer, Energía, Innovación y Desarrollo Fotovoltaico, SA, the closure of the file represents the loss of all resources invested in the process since 2021: environmental studies, engineering, administrative fees, grid permits, and team time. A 70.8 MW project represents, in terms of typical sector investment, a figure of tens of millions of euros in pre-construction development, although the resolution does not quantify this amount.
For the photovoltaic sector as a whole, the resolution has a signaling impact:
- The unfavorable DIA of April 24, 2026 shows that the administration applies strict environmental criteria in the southeastern peninsula, an area with high pressure from renewable projects.
- The expiration of grid permits in February 2024—more than two years before the resolution—shows that environmental processing timelines can exceed the validity of connection permits, creating a systemic risk for projects with long processing times.
- The developer's failure to submit comments is a procedural error that any active developer must avoid: the public hearing procedure is the last opportunity to influence the resolution.
Who does it affect?
- Energía, Innovación y Desarrollo Fotovoltaico, SA: direct developer, with the file definitively closed.
- Photovoltaic developers with projects in process in Murcia and Alicante: must review the status of their grid access and connection permits and the progress of their environmental impact studies.
- Investors and funds with exposure to development projects (greenfield) in the southeastern peninsula: the denial affects renewable energy planning in the area.
- Legal advisors and consultants for renewable project processing: must incorporate monitoring of grid permit validity as a critical control in any project.
- Photovoltaic project portfolio managers: need to audit the status of connection permits in all development assets.
Practical example
Imagine a developer with a 50 MW photovoltaic project in process in Murcia province. It obtained grid access and connection permits in 2022 with a validity of 24 months. In 2024 they expired, but the processing team was focused on the environmental assessment procedure and did not renew the permits in time.
In 2026, when the General Directorate of Energy Policy and Mines reviews the file, it finds itself in exactly the same situation as Rojalinda: expired grid permits. Even if the environmental impact study were favorable, prior administrative authorization cannot be granted without valid grid permits. The result: file closure and loss of all investment in processing.
The direct lesson from the Rojalinda case: the validity of grid access and connection permits must be monitored continuously and renewed proactively, without waiting for the environmental procedure to conclude.
What should companies do now?
- Audit the status of grid access and connection permits for all photovoltaic projects in process. Verify expiration dates and activate renewals with sufficient advance notice.
- Review the progress of the environmental assessment procedure for each project. If there are signs that the DIA may be unfavorable, consider whether it makes sense to keep grid permits active or renegotiate the position at the substation.
- Establish a protocol for monitoring public hearing procedures. The failure to submit comments in the Rojalinda case was an avoidable error. Any notification of a public hearing procedure must trigger an immediate response from the legal team.
- Evaluate environmental viability before renewing grid permits in projects with prolonged processing. If the DIA has a high probability of being unfavorable, the cost of renewing permits may not be justified.
- Incorporate permit expiration alerts in project portfolio management systems, with automatic notifications at least 6 months before expiration.
Frequently asked questions
Why was the Rojalinda solar plant denied?
For two cumulative reasons: the environmental impact declaration issued on April 24, 2026 was unfavorable, concluding that the project would cause significant negative impacts without sufficient possibility of correction; and the grid access and connection permits at the Rojales 220 kV substation expired in February 2024, being an essential requirement to obtain prior administrative authorization.
Can the developer appeal or reactivate the Rojalinda project?
The resolution definitively closes the file initiated in 2021. The developer did not submit comments during the public hearing procedure, which significantly limits the possibilities for appeal. To reactivate the project, it would need to initiate a new file from scratch, which would involve obtaining new grid permits and overcoming a new environmental assessment procedure.
What happens if grid access and connection permits for my photovoltaic project expire?
The expiration of grid access and connection permits is sufficient grounds to deny prior administrative authorization, regardless of the environmental procedure outcome. As occurred in Rojalinda, the permits expired in February 2024 and the denial resolution was issued in October 2026. It is essential to renew them before expiration.
What is an unfavorable environmental impact declaration and what are its consequences?
An unfavorable environmental impact declaration (DIA) is the pronouncement of the competent environmental authority concluding that a project would cause significant negative impacts that cannot be sufficiently corrected. In the case of Rojalinda, the unfavorable DIA was issued on April 24, 2026 and is, by itself, sufficient legal grounds to deny prior administrative authorization for the installation.
How does this denial affect renewable energy planning in Murcia and Alicante?
The resolution closes a 70.8 MW project in the southeastern peninsula, affecting renewable energy planning in the area. It indicates that the administration applies strict environmental criteria in this area, with high pressure from renewable projects, and that environmental processing timelines can exceed the validity of grid connection permits, which represents a systemic risk for other projects in process.
Official source
Consult complete regulation at official source