Energy

Otero Solar Park (431 MW, Segovia): keys to the favorable EIA for the renewable sector

E
Equipo Editorial CambiosLegales
20 Jun 2026 7 min 3 views

Key data

RegulationResolution of May 29, 2026, DGCEA — Environmental Impact Statement of the photovoltaic solar park "Otero"
BOE PublicationJune 20, 2026
Entry into forceJune 20, 2026
PromoterIberenova Promociones SAU
Installed capacity431.644 MW
Occupied area923 hectares
LocationProvince of Segovia (several municipalities)
Evacuation infrastructureUnderground 400 kV line to the Abades substation
Previous EIAUnfavorable in 2021 on a 505 MW project
CategoryEnergy / Environmental assessment
Year2026
Impact analysis reserved for PRO
The detailed impact analysis of this regulation is available for users with a PRO plan or higher. Access the full content and receive personalized alerts.
From €9.99/month · Cancel anytime

Iberenova Promociones SAU manages to unlock the largest solar park in the province of Segovia: 431.644 MW over 923 hectares, with underground 400 kV evacuation to the Abades substation. The Resolution of May 29, 2026 from the Directorate General for Quality and Environmental Assessment formulates the favorable environmental impact statement (EIA), published in the BOE on June 20, 2026.

The path has not been easy: in 2021 there was an unfavorable EIA on a similar project of 505 MW. The current project is a reduced and adapted version that eliminated the most conflictive sectors, cutting capacity by more than 73 MW and the surface area to fit within acceptable environmental thresholds.

431.644 MW
Approved installed capacity
923 ha
Occupied area (after eliminating conflictive sectors)
400 kV
Voltage of the underground evacuation line to Abades substation
505 MW → 431 MW
Reduction compared to the 2021 unfavorable EIA project

What does this regulation establish?

The resolution formulates the favorable EIA of the photovoltaic solar park "Otero", which enables the promoter to continue with the following administrative phases of the project (substantive authorization, municipal licenses, etc.). Without a favorable EIA, the project cannot move forward.

The key technical and environmental elements are:

ElementDetail
Installed capacity431.644 MW
Area923 hectares (after eliminating conflictive sectors)
Evacuation infrastructureUnderground 400 kV line to the Abades substation
Conditioning speciesMontagu's harrier and great bustard (protected steppe birds)
Faunal sensitivityHigh across virtually the entire project surface
Protected areas affectedNatura 2000 Network zones
Imposed measuresSpecific compensatory measures for fauna and Natura 2000 areas
Previous processMultiple information extensions and additional field studies
PrecedentUnfavorable EIA from 2021 on a 505 MW project

The complexity of the proceedings has been especially high: the impact on steppe birds such as the montagu's harrier and the great bustard required multiple information extensions and additional field studies before being able to issue a favorable resolution. The selected alternative affects areas of high sensitivity for birds across virtually its entire surface, which has directly conditioned the content of the EIA with specific compensatory measures.

Economic and operational impact

For Iberenova Promociones SAU, the favorable EIA means unlocking a large-scale investment in solar energy. A 431 MW park represents one of the largest photovoltaic installations in Castilla y León.

For the renewable sector in general, this resolution sends clear signals about the operational and temporal cost of projects in sensitive areas:

  • Extended processing time: the process has required multiple rounds of additional information and field studies, significantly extending the timeline compared to projects in areas of lower sensitivity.
  • Power reduction as a strategy: moving from 505 MW (unfavorable EIA, 2021) to 431.644 MW (favorable EIA, 2026) demonstrates that adapting the project — eliminating conflictive sectors — is the way to overcome environmental assessment in environments with steppe birds.
  • Permanent operational conditions: compensatory measures for fauna and Natura 2000 areas imply additional costs for monitoring, environmental surveillance, and possible restrictions in construction and operation phases.
  • Underground infrastructure: evacuation via underground 400 kV line to the Abades substation has a higher cost than conventional overhead line, but was a necessary condition for the environmental viability of the project.

Who does it affect?

  • Iberenova Promociones SAU: direct promoter, which can now advance in the substantive authorizations of the project.
  • Affected municipalities in Segovia: the town councils in the implementation area must process licenses and manage territorial impact.
  • Solar park promoters in cereal steppe areas: any company with projects in areas with montagu's harrier, great bustard, or other steppe birds should anticipate longer processes and more demanding conditions.
  • Engineering and environmental consulting companies: the complexity of the proceedings reinforces the need for exhaustive field studies from the beginning of the project.
  • Investors in renewables in Castilla y León: the resolution establishes a precedent on what type of adaptations allow overcoming a previous unfavorable EIA.
  • Network operators and electrical infrastructure managers: the connection to the Abades substation at 400 kV affects network planning in the area.

Practical example

A renewable energy promoter has a 500 MW solar project in a cereal area of Segovia with confirmed presence of great bustard and montagu's harrier. Based on the Otero case, the most likely scenario is:

  • The initial EIA may result in unfavorable if the project does not eliminate the sectors of greatest faunal sensitivity.
  • To obtain a favorable EIA, the company must reduce capacity and area, eliminating sectors that overlap with breeding and ranging areas of steppe birds — in the Otero case, the reduction was from 505 MW to 431.644 MW (more than 73 MW eliminated).
  • The process will require multiple additional field studies and information extensions, which can extend the proceedings several years.
  • Evacuation must be planned as an underground line to minimize impact on birds.
  • Once the favorable EIA is obtained, the project will be conditioned to specific compensatory measures for fauna and Natura 2000 during the entire useful life of the installation.

Do you need to monitor this and other regulations?

Check the full details in CambiosLegales

What should companies do now?

  1. Review projects in portfolio with presence of steppe birds: identify which installations are located in areas with montagu's harrier, great bustard, or other species of high sensitivity and anticipate the need for additional field studies.
  2. Analyze the power reduction strategy: if a project faces an unfavorable EIA or risk of it, evaluate the elimination of conflictive sectors as a way to obtain environmental approval, following the Otero model.
  3. Plan underground evacuation infrastructure: in areas of high faunal sensitivity, budget from the start the underground option for the evacuation line, as it may be a sine qua non condition for the favorable EIA.
  4. Incorporate compensatory measures in the business plan: conditions for fauna and Natura 2000 areas generate recurring operational costs (monitoring, environmental surveillance) that must be reflected in the project's financial model.
  5. Consult the complete resolution in the BOE: the specific conditions imposed in the EIA of the Otero park are direct reference for similar projects in the same geographic area.

Frequently asked questions

What capacity does the Otero solar park have and where is it located?

The photovoltaic solar park "Otero" has an installed capacity of 431.644 MW and is located in the province of Segovia, in several municipalities. It occupies an area of 923 hectares after the elimination of the most conflictive sectors from an environmental perspective.

Why was there a previous unfavorable EIA and how was it overcome?

In 2021 there was an unfavorable environmental impact statement on a similar project of 505 MW. The current project overcomes that resolution through a reduced and adapted version: sectors that generated the greatest conflict with protected steppe birds (montagu's harrier and great bustard) were eliminated, reducing capacity by more than 73 MW and adjusting the occupied area.

What environmental conditions does the favorable EIA of the Otero park impose?

The favorable EIA includes specific compensatory measures for fauna and Natura 2000 areas, given that the selected alternative affects areas of high sensitivity for birds across virtually its entire surface. The main conditioning species are the montagu's harrier and the great bustard. Additionally, the evacuation infrastructure must be underground (400 kV to the Abades substation).

When does the EIA of the Otero solar park come into force?

The resolution was published in the BOE on June 20, 2026 and came into force on that same date. The promoter, Iberenova Promociones SAU, can from that moment advance in the following phases of project authorization.

What are the implications of this resolution for other solar park promoters in areas with steppe birds?

This resolution establishes a clear precedent: projects in areas of high faunal sensitivity (steppe birds, Natura 2000) require multiple additional field studies, may need significant reductions in capacity and area, and must incorporate permanent compensatory measures. The process can extend several years compared to projects in areas of lower sensitivity.

Official source

Consult complete regulation in official source

Notice: This article is merely informative in nature and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-13448



Share:
E
Equipo Editorial CambiosLegales

El equipo editorial de CambiosLegales analiza diariamente los cambios normativos que afectan a empresas y autónomos en España, ofreciendo análisis pro...

Comments

No comments yet. Be the first to comment!

Leave a comment
Get free alerts