17.5 MW Battery in A Coruña: what it means for the renewable sector in 2026

E
Equipo Editorial CambiosLegales
Oct 19, 2026 7 min 18 views

Key data

RegulationResolution of September 29, 2026, from the General Directorate of Energy Policy and Mines
PublicationOctober 19, 2026
Entry into forceOctober 19, 2026
PromoterEnel Green Power España, SL
Authorized installationTesouro Storage — battery storage system
Battery capacity17.5 MW
Hybridized wind farmTesouro — 50.4 MW
LocationAs Pontes de García Rodríguez (A Coruña)
CategoryEnergy
Year2026
Impact analysis reserved for subscribers
The detailed impact analysis of this regulation is available with the PRO and Business plans. Access the full content and receive personalized alerts.
From €9.99/month · Cancel anytime

Enel Green Power España, SL, can now proceed with the construction of Tesouro Storage, a battery storage installation of 17.5 MW that will be integrated with the Tesouro wind farm of 50.4 MW in As Pontes de García Rodríguez (A Coruña). The Resolution of September 29, 2026 from the General Directorate of Energy Policy and Mines grants both prior administrative authorization and administrative construction authorization, published in the BOE on October 19, 2026.

This project does not start from scratch: it leverages access and connection permits already granted at the Puentes G.R. 400 kV substation of Red Eléctrica de España, which significantly reduces project timelines and administrative complexity.

17.5 MW
Power of the Tesouro Storage battery storage system
50.4 MW
Power of the Tesouro wind farm with which it will be hybridized
33 kV
Voltage of underground evacuation circuits
400 kV
Voltage of the Puentes G.R. substation of Red Eléctrica de España

What does this regulation establish?

The resolution grants Enel Green Power España two simultaneous authorizations for the Tesouro Storage project:

  • Prior administrative authorization: recognizes the project's viability from an energy perspective and its fit within the electrical system planning.
  • Administrative construction authorization: enables the effective start of works and installations.

The authorized infrastructure includes the following technical elements:

ElementDetail
Storage systemBatteries of 17.5 MW installed capacity
Evacuation circuitsUnderground at 33 kV
Sectioning centerNew, included in the project
Existing substationExpansion of the substation already in service
Grid connection pointPuentes G.R. 400 kV substation (Red Eléctrica de España)

The file was submitted for consultation to multiple agencies. The Dirección Xeral de Saúde Pública questioned whether an additional environmental assessment was necessary, but the promoter ruled out this need under the Law 21/2013 on environmental assessment, with no agency presenting decisive opposition to the project.

Economic and operational impact

Wind-battery hybridization is one of the business models with the greatest projection in the Spanish energy sector. It allows the promoter to optimize the use of network access permits already granted, avoiding the processing of new connection points, which is one of the main bottlenecks in renewable development in Spain.

For Enel Green Power España, the operational advantages are direct:

  • Reuse of the existing evacuation infrastructure of the Tesouro wind farm.
  • Guaranteed access to the Puentes G.R. 400 kV substation without the need to process new connection permits.
  • Ability to store wind energy during periods of low demand and release it to the grid during periods of high demand or price, improving asset profitability.
  • Competitive positioning in the market for electrical system adjustment services, where storage has increasing economic value.

For the sector as a whole, this authorization consolidates the regulatory framework for hybridization projects in Spain and reinforces the signal that the Administration supports this type of investment without requiring new environmental assessments when the project correctly complies with Law 21/2013.

Who does it affect?

  • Enel Green Power España, SL: direct promoter and holder of the granted authorizations.
  • Promoters of wind farms in Galicia and Spain studying hybridization with storage: this resolution is an applicable precedent for similar projects.
  • Companies in the energy storage sector (battery manufacturers and integrators) participating in the project supply chain.
  • Network operators and managers of the Puentes G.R. 400 kV substation (Red Eléctrica de España), who must coordinate the expansion of the existing substation.
  • Energy advisors and consultants managing wind-battery hybridization files before the General Directorate of Energy Policy and Mines.
  • Investors and renewable infrastructure funds evaluating wind assets in Spain with hybridization potential.

Practical example

A wind farm promoter with an operating park with access and connection permits already granted can follow the Tesouro Storage model to add storage capacity without processing a new grid connection point.

In the specific case of Tesouro: the wind farm has 50.4 MW of installed capacity. The authorized battery represents 34.7% of that capacity (17.5 MW out of 50.4 MW). This means that, at times of maximum generation, the battery can absorb approximately one-third of the park's production to release it later when market price or system needs are more favorable.

The key to the file is that the promoter avoided an additional environmental assessment by invoking Law 21/2013, which significantly expedited the processing. Any promoter in a similar situation should analyze whether their project meets the assumptions of that law before initiating the file, as it can mean months of difference in authorization timelines.

Do you need to monitor this and other regulations?

Check the full details on CambiosLegales

What should companies do now?

  1. Review existing access and connection permits in own wind farms: if already granted, they are the basis for processing a battery hybridization without the need for new network permits.
  2. Analyze the technical feasibility of hybridization in installations with spare evacuation capacity, calculating the optimal ratio between wind power and battery power.
  3. Verify compliance with Law 21/2013 before initiating the administrative file, to determine whether the project requires additional environmental assessment and plan timelines accordingly.
  4. Identify the connection substation and coordinate with Red Eléctrica de España the conditions for necessary expansion, as has been done in Tesouro with the Puentes G.R. 400 kV substation.
  5. Prepare technical documentation for the simultaneous application for prior administrative authorization and construction authorization before the General Directorate of Energy Policy and Mines, following the model of this file.
  6. Monitor similar resolutions published in the BOE to identify applicable administrative precedents for own projects in process.

Frequently asked questions

What is wind-battery hybridization and why is it relevant for the sector?

Hybridization consists of connecting a battery storage system to an existing wind farm, sharing evacuation infrastructure and grid connection permits. In the case of Tesouro Storage, a 17.5 MW battery will be hybridized with the Tesouro wind farm of 50.4 MW in As Pontes de García Rodríguez (A Coruña). The main advantage is that it avoids processing new network access permits, which are one of the main obstacles to renewable development in Spain.

What authorizations has Enel Green Power obtained for Tesouro Storage?

The Resolution of September 29, 2026 from the General Directorate of Energy Policy and Mines grants two simultaneous authorizations: prior administrative authorization and administrative construction authorization. Both were published in the BOE on October 19, 2026 and entered into force on that same date.

What infrastructure does the Tesouro Storage project include?

The project includes the 17.5 MW battery storage system, underground evacuation circuits at 33 kV, a new sectioning center and the expansion of the existing substation. Grid connection will be made through the Puentes G.R. 400 kV substation of Red Eléctrica de España, leveraging access permits already granted for the Tesouro wind farm.

Is an additional environmental assessment necessary for hybridization projects like this?

In the case of Tesouro Storage, the promoter ruled out the need for additional environmental assessment under Law 21/2013 on environmental assessment. The Dirección Xeral de Saúde Pública questioned this matter during agency consultation, but did not present decisive opposition. No consulted agency blocked the project. Each promoter must analyze their specific case based on project characteristics and applicable regulations.

What other promoters can replicate this hybridization model?

Any wind farm promoter in Spain with access and connection permits already granted can study hybridization with storage following the Tesouro Storage model. The key is to leverage existing evacuation infrastructure and verify compliance with Law 21/2013 to expedite administrative processing before the General Directorate of Energy Policy and Mines.

Official source

Consult complete regulation at official source

Notice: This article is for informational purposes only and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-21769



Share:
E
Equipo Editorial CambiosLegales

El equipo editorial de CambiosLegales analiza diariamente los cambios normativos que afectan a empresas y autónomos en España, ofreciendo análisis pro...

Comments

No comments yet. Be the first to comment!

Leave a comment
Activate alerts

Almost there