21.56 MW Battery in Esquivias: Key insights for the solar sector in Toledo

E
Equipo Editorial CambiosLegales
Oct 12, 2026 6 min 1 views

Key data

RegulationResolution of September 7, 2026, from the General Directorate of Energy Policy and Mines
BOE PublicationOctober 12, 2026
Entry into forceNot specified in the resolution
Holding companyMulhacén Solar, SLU
Storage module power21.56 MW
Existing photovoltaic plant power70 MW
LocationEsquivias (Toledo), Castilla-La Mancha
Evacuation voltage30 kV (underground lines)
Connection substationNumancia 4
Final transport networkTorrejón de Velasco 400 kV
Regulatory frameworkRD 997/2025 and Law 24/2013 of the Electricity Sector
Update of access/connection permitsRed Eléctrica de España, November 2023
CategoryEnergy
Impact analysis reserved for subscribers
The detailed impact analysis of this regulation is available with the PRO and Business plans. Access the full content and receive personalized alerts.
From €9.99/month · Cancel anytime

Mulhacén Solar, SLU can now execute its energy storage module of 21.56 MW in Esquivias (Toledo) after receiving prior administrative authorization from the General Directorate of Energy Policy and Mines, published in the BOE on October 12, 2026. The resolution, signed on September 7, 2026, enables hybridization of this battery with the Mulhacén Solar photovoltaic plant, already operational with 70 MW of installed capacity.

The authorization is based on RD 997/2025 and Law 24/2013 of the Electricity Sector, and is granted without prejudice to other sectoral authorizations that the promoter must obtain. For the renewable sector, this resolution is a clear signal that the administration is streamlining solar-storage hybridization procedures in Spain.

21.56 MW
Power of the authorized storage module
70 MW
Power of the existing photovoltaic plant to hybridize
30 kV
Evacuation voltage via underground lines
400 kV
Voltage of the transport network in Torrejón de Velasco

What does this regulation establish?

The resolution grants prior administrative authorization for the project called "Mulhacén energy storage module," along with its evacuation infrastructure. The key technical and regulatory elements are as follows:

ElementDetail
Type of installationEnergy storage module (battery)
Installed power21.56 MW
Installation with which it hybridizesMulhacén Solar photovoltaic plant (70 MW)
Evacuation infrastructureUnderground lines at 30 kV connected to Numancia 4 substation
Connection to transport networkAlready authorized infrastructure up to Torrejón de Velasco 400 kV
Environmental assessmentSimplified — without need for ordinary procedure
Access and connection permitsUpdated by Red Eléctrica de España in November 2023
Applicable legal frameworkRD 997/2025 and Law 24/2013 of the Electricity Sector

A notable aspect is that evacuation takes advantage of already authorized infrastructure, which reduces administrative complexity and execution timelines. Connection to the Numancia 4 substation at 30 kV via underground lines is the technical solution chosen to integrate storage into the existing network.

Economic and operational impact

Hybridization of a 21.56 MW battery with a 70 MW solar plant has direct operational and economic implications for Mulhacén Solar, SLU and serves as a model for the sector:

  • Revenue optimization: The battery allows storing energy generated during low-demand hours and releasing it to the grid during peak hours, improving average selling price.
  • Reduction of spillage: In large photovoltaic plants, storage prevents generated energy from being wasted when the grid cannot absorb it.
  • Leveraging existing infrastructure: By using evacuation lines and access permits already authorized (updated by Red Eléctrica in November 2023), the promoter avoids costs and additional timelines for new connections.
  • Environmental agility: Passing simplified environmental impact assessment without ordinary procedure shortens the startup calendar and reduces regulatory uncertainty.
  • Consolidated regulatory framework: RD 997/2025 and Law 24/2013 provide a predictable framework for structuring financing of hybridization projects.

Who does it affect?

  • Mulhacén Solar, SLU: Direct holder of the authorization and responsible for executing the project.
  • Renewable energy promoters in Castilla-La Mancha: The resolution establishes a precedent on how to process solar-storage hybridizations under RD 997/2025.
  • Investors and renewable funds: The authorization confirms the regulatory viability of storage projects associated with existing photovoltaic plants in Spain.
  • Legal and technical advisors in the energy sector: Must understand the simplified environmental assessment procedure and updated access and connection requirements by Red Eléctrica de España.
  • Network operators and substations: Red Eléctrica de España, as manager of the transport network in Torrejón de Velasco (400 kV), and operators of the Numancia 4 substation.

Practical example

A promoter already operating a 70 MW photovoltaic plant in Toledo province and wanting to add storage can follow the path traced by Mulhacén Solar:

  1. Request update of access and connection permits from Red Eléctrica de España — in Mulhacén Solar's case, this step was completed in November 2023.
  2. Submit the storage module project to the General Directorate of Energy Policy and Mines, under RD 997/2025 and Law 24/2013.
  3. Opt for simplified environmental impact assessment if project characteristics allow, avoiding ordinary procedure and shortening timelines.
  4. Design evacuation via underground lines at 30 kV connected to an existing substation, leveraging already authorized infrastructure up to the transport network.

In Mulhacén Solar's specific case, the 21.56 MW battery represents approximately 30.8% of the power of the 70 MW photovoltaic plant, a typical proportion in hybridization projects seeking to balance investment cost and energy management capacity.

Need to track this and other regulations?

Check full details on CambiosLegales

What should companies do now?

  1. Review if you have photovoltaic plants susceptible to hybridization: If you operate solar installations in Spain, analyze whether adding storage improves your profitability and if your access and connection permits are up to date.
  2. Verify the status of your access and connection permits with Red Eléctrica de España: They are an essential prerequisite for any hybridization request under RD 997/2025.
  3. Study the simplified environmental assessment route: If the project does not exceed thresholds requiring ordinary procedure, this route significantly shortens authorization timelines.
  4. Leverage already authorized evacuation infrastructure: Connecting the storage module to existing lines and installations reduces costs and additional procedures.
  5. Consult the RD 997/2025 and Law 24/2013 framework: These are the regulations governing the prior administrative authorization procedure for this type of project in Spain.
  6. Follow regulatory developments in Castilla-La Mancha: The region concentrates a relevant portion of installed photovoltaic capacity in Spain; regional and state resolutions in this community set trends for the rest of the territory.

Frequently asked questions

What is prior administrative authorization and what does it allow Mulhacén Solar to do?

Prior administrative authorization is the first formal permit that enables a promoter to execute an energy installation project. In this case, it allows Mulhacén Solar, SLU to build and operate a 21.56 MW storage module in Esquivias (Toledo), hybridized with its 70 MW photovoltaic plant. It is granted under RD 997/2025 and Law 24/2013 of the Electricity Sector, and does not exempt from other necessary sectoral authorizations.

How will energy from Mulhacén Solar's storage module be evacuated?

Via underground lines at 30 kV connected to the Numancia 4 substation. From there, already authorized infrastructure is leveraged that reaches the transport network in Torrejón de Velasco at 400 kV. This design reuses existing connections, simplifying procedures and reducing infrastructure costs.

Why was ordinary environmental impact assessment not necessary?

The project passed simplified environmental impact assessment without needing to undergo ordinary procedure. This occurs when project characteristics (size, location, potential impact) do not exceed thresholds requiring complete procedure. For Mulhacén Solar, this meant a significant reduction in timelines and administrative procedures.

What regulation governs hybridization of solar plants with batteries in Spain?

The main framework is RD 997/2025 and Law 24/2013 of the Electricity Sector. These texts regulate the prior administrative authorization procedure, construction and operation of electricity production and storage installations. Access and connection permits to the transport network are managed by Red Eléctrica de España.

When were Mulhacén Solar's access and connection permits updated?

Access and connection permits were updated by Red Eléctrica de España in November 2023. This update was a prerequisite for the General Directorate of Energy Policy and Mines to grant prior administrative authorization published in the BOE on October 12, 2026.

Official source

Consult complete regulation at official source

Notice: This article is purely informational in nature and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-21226



Share:
E
Equipo Editorial CambiosLegales