Key data
| Regulation | Resolution of November 11, 2026, from the Territorial Delegation of Bizkaia, Department of Industry, Energy Transition and Sustainability |
|---|---|
| Publication | November 25, 2026 |
| Entry into force | November 25, 2026 |
| Affected parties | Electrical sector companies, network operators and installers using measurement equipment |
| Category | Energy |
| Authorized manufacturer | AIT, SA (Argentine company of the Arteche group) |
| Authorized models | CA-145, CA-245, UT-145 and UT-245 |
| Validity | 5 years, renewable |
| Territorial scope | Entire national territory |
| Legal basis | Royal Decree 1110/2007, on measurement points of the electrical system |
Network operators and installers in the electrical sector can now use AIT, SA measurement transformers in their installations in Spain. The Territorial Delegation of Bizkaia published on November 25, 2026 the resolution that provisionally authorizes four specific models from this Argentine company, belonging to the Arteche group, with validity throughout the national territory.
The authorization is based on Royal Decree 1110/2007, which regulates the measurement points of the electrical system, and is granted provisionally precisely because there is no specific metrological regulation for this type of equipment yet. When that regulation enters into force, the manufacturer must obtain the metrological conformity assessment within a maximum period of one year.
What does this regulation establish?
The resolution provisionally authorizes the installation and use in the Spanish electrical network of the following measurement transformer models manufactured by AIT, SA:
| Model | Manufacturer | Business group | Origin |
|---|---|---|---|
| CA-145 | AIT, SA | Arteche | Argentina |
| CA-245 | AIT, SA | Arteche | Argentina |
| UT-145 | AIT, SA | Arteche | Argentina |
| UT-245 | AIT, SA | Arteche | Argentina |
The authorization is provisional in nature because at the time of its granting there is no specific metrological regulation for these equipment. The key conditions established by the resolution are:
- Mandatory origin verification: each equipment must pass an origin verification performed by an authorized verifier before being installed in the network.
- Metrological conformity period: the manufacturer (AIT, SA) must obtain the metrological conformity assessment within one year from the entry into force of the applicable specific metrological regulation.
- New authorization for modifications: any modification in the design of the equipment will require a new authorization. It is not possible to install modified versions under the protection of this resolution.
- National scope: the authorization is valid throughout Spanish territory, not just in the Basque Country.
- Validity: 5 years from publication (November 25, 2026), renewable.
Economic and operational impact
For electrical sector companies, this resolution has mainly an operational impact. The four authorized models can be incorporated into the purchasing, bidding and installation processes of measurement equipment without needing to wait for additional authorization, which expands the catalog of available suppliers.
However, the obligation to verify equipment at origin by an authorized verifier before each installation implies an additional step in the logistics and supply chain. Companies must anticipate this procedure in their work planning and supply contracts, as installing equipment without this prior verification would constitute a breach of the authorization conditions.
The most relevant medium-term economic risk is the metrological conformity period: when the specific metrological regulation for these equipment enters into force, AIT, SA will have one year to obtain the conformity assessment. If it fails to do so within that period, the provisional authorization could become void, affecting already installed equipment and ongoing contracts.
Who does it affect?
- Distribution and electrical transmission network operators that acquire or install measurement transformers in their networks.
- Installation companies of measurement equipment in electrical installations connected to the network.
- Purchasing and supply departments of utilities and energy companies that include the CA-145, CA-245, UT-145 or UT-245 models in their supplier catalogs.
- Technical and regulatory compliance managers in electrical sector companies that must ensure installed equipment has current authorizations.
- Authorized verifiers who must perform the origin verification of each equipment before installation.
- AIT, SA and the Arteche group, as the manufacturer required to obtain the metrological conformity assessment within the established period.
Practical example
An electrical distributor operating in several autonomous communities decides to incorporate the UT-245 model from AIT, SA into its next bidding process for measurement equipment to renovate substations.
Thanks to this resolution, it can include the UT-245 in the technical specifications without needing to process additional authorization, since the resolution is valid throughout the national territory. However, before installing each unit in the network, it must prove that the equipment has passed the origin verification by an authorized verifier. This involves coordinating with the supplier so that the verification is documented and available before commissioning.
Additionally, the distributor's technical manager must include in their regulatory monitoring calendar the moment when the specific metrological regulation for these equipment enters into force, as from that point AIT, SA will have 1 year to obtain the conformity assessment. If the manufacturer fails to obtain it, the company must review contracts and the plan for ongoing installations.
What should companies do now?
- Verify if you use any of the four authorized models (CA-145, CA-245, UT-145 or UT-245) in your current or future projects, and confirm that installation is carried out under the protection of this resolution.
- Require origin verification from your supplier or authorized verifier before installing any equipment of these models. Document the result and keep it as part of the installation file.
- Review supply contracts with AIT, SA or distributors of the Arteche group to include clauses that guarantee compliance with the metrological conformity period (1 year from the entry into force of the specific regulation).
- Do not install equipment with modified design without processing a new authorization: any variation from the authorized model requires a new process.
- Activate regulatory alerts to detect when the specific metrological regulation enters into force, as that moment activates the 1-year period for manufacturer conformity.
Frequently asked questions
What measurement transformer models from AIT, SA are authorized in Spain?
The resolution of November 25, 2026 authorizes four models: CA-145, CA-245, UT-145 and UT-245. All are manufactured by AIT, SA, an Argentine company of the Arteche group. The authorization is valid throughout the national territory and has a validity period of 5 years, renewable.
Is it mandatory to verify transformers before installing them?
Yes. The resolution establishes that each equipment must pass an origin verification performed by an authorized verifier before its installation in the network. It is not enough that the model is authorized: each individual unit must pass this prior control.
How much time does AIT, SA have to obtain metrological conformity?
The manufacturer has 1 year from the entry into force of the applicable specific metrological regulation to obtain the metrological conformity assessment. While that regulation does not exist, the provisional authorization remains in force.
What happens if the design of authorized equipment is modified?
Any modification in the design of authorized models requires processing a new authorization. Modified equipment is not covered by the current resolution, so installing them without new authorization would constitute regulatory non-compliance.
Is this authorization valid outside the Basque Country?
Yes. Although the resolution is issued by the Territorial Delegation of Bizkaia, the authorization is valid throughout Spanish national territory. Companies from any autonomous community can install these equipment under the protection of this resolution.
Official source