Solar hybridization denied in Burgos: what it means for renewable promoters in 2026
The photovoltaic plant «El Gallo» (16.18 MW) in Burgos will not obtain state authorization: by falling below 50 MW, comp...
12 Articles
The photovoltaic plant «El Gallo» (16.18 MW) in Burgos will not obtain state authorization: by falling below 50 MW, comp...
The photovoltaic hybridization of La Zarzuela (13.685 MW) is denied by the State: as it is reduced to 0.3 MW, hybrid pow...
On November 11, 2026, there is a general strike. Electric companies must maintain full availability in generation, trans...
Naturgy appeals to the National Court the CNMC resolution that requires dynamic voltage control performance. What it mea...
Naturgy Renewables obtains authorization to install a 19.8 MW battery module alongside its 48.8 MW solar plant in Tabern...
Greenalia renounces the Nordés wind farm (67.2 MW) in Lugo and A Coruña due to lack of grid access. The developer recove...
Greenalia abandons the 106.4 MW Mistral wind farm in Lugo due to lack of grid access. Guarantees of €5.824 million at st...
A 26.74 MW battery authorized to hybridize with the Los Arcos solar plant (43.90 MW) in Andorra (Teruel). Simplified pro...
The 50.88 MW expansion of El Páramo wind park (León) has been denied due to unfavorable EIA and expired grid connection ...
Iberdrola loses authorization for its 43.89 MW solar plant in Soria due to expiration of access permits. A critical warn...
Azor Solar obtains authorization for a 68.51 MW battery in Paracuellos de Jarama, hybridized with its 64.02 MW solar pla...
The State Secretariat for Energy updates operation remuneration (Ro) for Q4 2026. Renewable, cogeneration and waste faci...