Energy

New 400 kV electrical line Teruel 2026: what it means for landowners and municipalities

E
Equipo Editorial CambiosLegales
07 Aug 2026 7 min 18 views

Key data

RegulationResolution of July 16, 2026, from the General Directorate of Energy Policy and Mines
BOE PublicationAugust 7, 2026
Effective dateAugust 7, 2026
PromoterRed Eléctrica de España, SAU
Route lengthApproximately 57.8 km
Voltage400 kV, double circuit, overhead line
SectionMezquita 400 kV Substation (Mezquita de Jarque) — Platea 400 kV Substation (Teruel)
ProvinceTeruel (Aragón)
Planning frameworkTransport Network Development Plan 2021-2026
CategoryEnergy / Electrical Infrastructure
Year2026
Impact analysis reserved for subscribers
The detailed impact analysis of this regulation is available with the PRO and Business plans. Access the full content and receive personalized alerts.
From €9.99/month · Cancel anytime

Landowners of properties in the route between Mezquita de Jarque and Teruel and the municipalities in the area have faced a new reality since August 7, 2026: the General Directorate of Energy Policy and Mines has granted Red Eléctrica de España, SAU administrative construction authorization and has declared the public utility of the installation.

The resolution, published in the BOE of August 7, 2026 (BOE-A-2026-17272), immediately activates the legal effects of the public utility declaration, which includes the possibility of initiating procedures for occupation of private land.

57.8 km
Total length of the route in Teruel province
400 kV
Line voltage, double circuit, overhead configuration
2021–2026
Transport Network Development Plan that includes this infrastructure

What does this regulation establish?

The resolution grants two simultaneous authorizations to Red Eléctrica de España:

  • Administrative construction authorization: permission to physically execute the double-circuit overhead line at 400 kV between the Mezquita 400 kV substation (municipality of Mezquita de Jarque) and the Platea 400 kV substation (Teruel).
  • Declaration of public utility: legal authorization that allows Red Eléctrica to occupy private land through forced easement or expropriation, regardless of opposition from landowners or municipalities.

A relevant element: the resolution expressly establishes that no municipal license or local preventive control act is required to begin construction. Several municipalities showed opposition or imposed conditions, but the declaration of public utility prevails over municipal planning objections.

To reduce environmental impact, an addendum to the original project was incorporated to minimize effects on the singular tree grove of the Ribera del Chopo Cabecero. The installation has a favorable environmental impact declaration.

Construction must comply with the conditions imposed by the following bodies:

BodyScope of conditions
INAGA (Aragonese Institute of Environmental Management)Environmental conditions and protection of flora and fauna
ADIFConditions for crossing or proximity to railway infrastructure
General Directorate of Roads of AragónConditions for crossing or proximity to the regional road network

Economic and operational impact

For landowners in the route, the declaration of public utility means that Red Eléctrica can initiate the procedure for imposing a right of way easement or forced expropriation. The owner has the right to compensation, but cannot block the project.

For affected municipalities, the resolution closes the avenue for planning objections. Municipalities that had conditioned or rejected the project cannot prevent the execution of works through licenses or local planning instruments. Their scope of action is limited to supervising compliance with applicable technical conditions in their municipal area.

For the energy sector and industrial companies in the area, the new infrastructure strengthens electrical transport capacity in Teruel province, which can translate into greater supply security and capacity to connect new renewable generation facilities to the system.

Who does it affect?

  • Red Eléctrica de España, SAU: promoter and responsible for execution, must comply with all conditions imposed by INAGA, ADIF and the General Directorate of Roads of Aragón.
  • Landowners in the route: exposed to forced easement or expropriation procedures along the 57.8 km route in Teruel province.
  • Affected municipalities in Teruel: those that showed opposition or conditions lose the ability to block the work through local planning instruments.
  • Companies with activity in the Ribera del Chopo Cabecero: the addendum to the project introduces specific restrictions to protect this singular tree grove, which may affect agricultural or forestry activities in the area.
  • Renewable energy promoters in Teruel: the new line expands electrical evacuation capacity in the area, opening opportunities for connection of new generation projects.

Practical example

A farmer with properties in the municipality of Mezquita de Jarque whose land falls within the 57.8 km line route receives a notification from Red Eléctrica de España initiating the right of way easement procedure.

Since the resolution of August 7, 2026 has already declared the public utility of the installation, the owner cannot oppose the occupation of the land, but does have the right to:

  • Participate in the valuation procedure to set the corresponding compensation.
  • Challenge the valuation if they consider it does not reflect the real value of the affected land.
  • Require that the execution of works respects the environmental conditions imposed by INAGA, especially regarding protection of the Ribera del Chopo Cabecero if their property is in that area.

A municipality that had conditioned the project in its municipal area, for its part, cannot deny a construction license or impose planning obstacles: the declaration of public utility exempts Red Eléctrica from obtaining municipal license or local preventive control act.

Do you need to monitor this and other regulations?

Check the full details on CambiosLegales

What should companies do now?

  1. Landowners: verify if their properties are included in the 57.8 km route and, if so, contact a lawyer specializing in expropriations to prepare the defense of their interests in the valuation procedure.
  2. Affected municipalities: review the technical conditions that apply in their municipal area (INAGA, ADIF, Roads of Aragón) and establish monitoring mechanisms for compliance during work execution.
  3. Companies with activity in the Ribera del Chopo Cabecero: consult the addendum to the project to learn about specific restrictions affecting this area and evaluate the impact on their activities.
  4. Renewable promoters in Teruel: analyze the new evacuation capacities that the Platea 400 kV substation in Teruel will provide and evaluate if it opens opportunities to connect new generation projects.
  5. Any affected party: consult the complete resolution in the BOE (BOE-A-2026-17272) to learn about the details of the conditions and applicable deadlines.

Frequently asked questions

Can a municipality block the construction of the electrical line in its municipality?

No. The resolution of August 7, 2026 expressly declares the public utility of the installation and establishes that no municipal license or local preventive control act is required. Several municipalities showed opposition or conditions, but the declaration of public utility prevails over municipal planning objections.

What happens if I have land in the 57.8 km route?

Red Eléctrica de España can initiate a procedure for imposing forced easement or expropriation on your land. The declaration of public utility has been in effect since August 7, 2026, so you cannot block the occupation, but you do have the right to compensation and to participate in the valuation procedure.

What conditions must Red Eléctrica comply with during construction?

The resolution imposes compliance with conditions from three bodies: INAGA (Aragonese Institute of Environmental Management), ADIF and the General Directorate of Roads of Aragón. Additionally, an addendum to the project was incorporated to minimize effects on the singular tree grove of the Ribera del Chopo Cabecero.

Is this line part of any energy planning plan?

Yes. The installation is included in the Transport Network Development Plan 2021-2026, the planning framework that defines the electrical transport infrastructure needed in Spain for that period.

When can Red Eléctrica begin the works?

The administrative construction authorization and the declaration of public utility came into effect on the same day of their publication in the BOE: August 7, 2026. Red Eléctrica is authorized to begin construction from that date, complying with the conditions imposed by INAGA, ADIF and the General Directorate of Roads of Aragón.

Official source

Consult complete regulation at official source

Notice: This article is for informational purposes only and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-17272



Share:
E
Equipo Editorial CambiosLegales

El equipo editorial de CambiosLegales analiza diariamente los cambios normativos que afectan a empresas y autónomos en España, ofreciendo análisis pro...