Key data
| Regulation | Resolution of September 3, 2026 from the Directorate General for Energy Policy and Mines |
|---|---|
| Publication | September 16, 2026 |
| Effective date | September 16, 2026 |
| Affected parties | Red Eléctrica de España SAU, landowners of affected properties and municipality of Sagunto (Valencia) |
| Category | Energy / Electrical infrastructure |
| Year | 2026 |
| Line voltage | 400 kV, double circuit |
| Declaration of public utility | Yes — enables forced expropriation of land |
| EIA (Environmental Impact Assessment) | May 2026 |
| Compensatory area | 10 hectares in Muntanyeta de les Lloses |
Landowners of properties along the route of the new Gaussa-Saguntum electrical transmission line in Sagunto (Valencia) may be affected by a forced expropriation procedure as of September 16, 2026. The Resolution of September 3, 2026 from the Directorate General for Energy Policy and Mines grants Red Eléctrica de España, SAU both prior administrative authorization and construction authorization, along with the declaration of public utility that activates this mechanism.
The infrastructure also includes the by-pass of the 400 kV lines Eliana-Gaussa and Morvedre-Gaussa 2, which expands the scope of the project beyond a simple new line.
What does this regulation establish?
The resolution grants three simultaneous authorizations to Red Eléctrica de España, SAU:
- Prior administrative authorization: approval of the project in the planning phase.
- Administrative construction authorization: permission to physically execute the works.
- Declaration of public utility: enables forced expropriation of private land necessary for the route.
The project comprises two distinct elements:
| Element | Technical description |
|---|---|
| Main line | 400 kV overhead transmission line, double circuit, Gaussa-Saguntum section |
| Eliana-Gaussa by-pass | Derivation on the existing 400 kV Eliana-Gaussa line |
| Morvedre-Gaussa 2 by-pass | Derivation on the existing 400 kV Morvedre-Gaussa 2 line |
The project passed environmental impact assessment with an Environmental Impact Assessment (EIA) issued in May 2026. That EIA imposes specific conditions that Red Eléctrica must comply with during construction and operation:
- Surveys of protected flora in the area of influence of the route.
- Compensatory forestry work in the Muntanyeta de les Lloses, covering an area of 10 hectares.
The Municipality of Sagunto, which initially opposed the project for urban planning and environmental reasons, ultimately issued a favorable report, unblocking the administrative process.
Economic and operational impact
For industrial companies installed or planned in Parc Sagunt, this authorization is good news: the new infrastructure strengthens the capacity and reliability of the electrical transmission network in the Comunitat Valenciana, reducing the risk of bottlenecks in high-voltage supply that feeds large industrial consumers.
For landowners along the route, the impact is the opposite: the declaration of public utility activates the forced expropriation procedure. This means that Red Eléctrica can initiate occupation of the necessary land, with corresponding assessed compensation, but without the ability to block the project once public utility has been declared.
The environmental conditions of the EIA (flora surveys and forestry work on 10 ha) fall on Red Eléctrica as the project promoter, not on third parties. However, companies in the surrounding area with agricultural or forestry activity in the Muntanyeta de les Lloses area should be alert to possible access or activity restrictions during the work.
Who is affected?
- Red Eléctrica de España, SAU: holder of the authorizations and responsible for project execution and compliance with EIA environmental conditions.
- Landowners along the route (Sagunto, Valencia): affected by the declaration of public utility and the resulting forced expropriation procedure.
- Parc Sagunt companies: beneficiaries of the reinforcement in the electrical transmission network and improved supply security.
- Large industrial consumers in the area: any company with high electrical demand in the Sagunto area and Comunitat Valenciana that depends on the 400 kV transmission network.
- Municipality of Sagunto: involved in the urban planning and environmental process, with a favorable report issued.
- Agricultural and forestry activities in Muntanyeta de les Lloses: possible temporary impact during compensatory forestry work on the 10 hectares.
Practical example
A company owning an agricultural plot in the municipality of Sagunto whose land falls within the route of the Gaussa-Saguntum line will receive formal notification of the start of forced expropriation proceedings from Red Eléctrica de España. Since public utility has been declared, the company cannot prevent land occupation, but it does have the right to participate in the valuation process and to challenge the fair price (compensation) if it disagrees with the proposed assessment. The timeline and specific conditions of each expropriation will be determined in the individual file, but the declaration of public utility is already in effect as of September 16, 2026.
On the other hand, a manufacturing company installed in Parc Sagunt with a high-voltage electrical supply contract can anticipate that the new infrastructure will improve local network redundancy, reducing the risk of interruptions due to saturation or failure in the current Eliana-Gaussa and Morvedre-Gaussa 2 circuits.
What should companies do now?
- Landowners in Sagunto: verify if your properties are included in the official route of the Gaussa-Saguntum line. If you receive expropriation notification, consult a lawyer specializing in forced expropriation before accepting the proposed fair price.
- Parc Sagunt companies and large industrial consumers: review with your electrical supply manager how the new infrastructure will affect your contracts and conditions for access to the transmission network.
- Agricultural or forestry activities in Muntanyeta de les Lloses: contact Red Eléctrica de España to learn about the schedule for forestry work on the 10 affected hectares and anticipate possible access restrictions.
- Any company with interests in the area: consult the complete resolution published in the BOE of September 16, 2026 to verify the exact route, EIA conditions and project timelines.
Frequently asked questions
What does it mean that public utility has been declared for the Gaussa-Saguntum line?
The declaration of public utility, included in the Resolution of September 3, 2026, enables Red Eléctrica de España, SAU, to initiate forced expropriation of private land necessary to build the line. Affected landowners have the right to compensation (fair price), but cannot block project execution.
What environmental conditions must Red Eléctrica comply with in Sagunto?
The Environmental Impact Assessment (EIA) of May 2026 imposes two main conditions: conduct surveys of protected flora in the area of influence of the route and execute compensatory forestry work in Muntanyeta de les Lloses covering an area of 10 hectares. These obligations fall on Red Eléctrica as the project promoter.
Which companies benefit from the electrical reinforcement in Sagunto?
Companies installed or planned in Parc Sagunt and large industrial consumers in the area are the main beneficiaries. The new 400 kV double-circuit overhead line, together with the by-pass of the Eliana-Gaussa and Morvedre-Gaussa 2 lines, strengthens the capacity and redundancy of the electrical transmission network in the Comunitat Valenciana.
When does the Gaussa-Saguntum line authorization take effect?
The resolution was published in the BOE on September 16, 2026 and took effect that same day. Prior administrative authorization, construction authorization and declaration of public utility are effective as of that date.
Did the Municipality of Sagunto ultimately support the project?
Yes. Although the Municipality of Sagunto initially opposed the project for urban planning and environmental reasons, it ultimately issued a favorable report, which allowed completion of the administrative process and obtaining the authorizations included in the September 2026 resolution.