Naturgy obtains permission to install 19.8 MW batteries next to its Tabernas solar plant (Almería)
21 Oct 20261 views
Who is affected:
Naturgy Renovables, SLU, and renewable energy sector with storage in Almería
Summary
The Ministry authorizes Naturgy to build a battery storage system to hybridize with its existing solar park in Tabernas, Almería. The installation will have 19.8 MW capacity.
Detailed analysis
PRO
The General Directorate of Energy Policy and Mines grants Naturgy Renovables, SLU, prior administrative and construction authorization for the BESS Tabernas I module (19.8 MW), which will be hybridized with the Tabernas I photovoltaic park (48.8 MW) already operational. Evacuation will be carried out via underground li…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 9 de mayo de 2025, de la Dirección General de Política Energética y Minas, por la que se otorga a Naturgy Renovables, SLU, la autorización administrativa previa y la autorización administrativa de construcción del módulo de almacenamiento por baterías «BESS Tabernas I», de 19,8 MW de potencia instalada, y para su infraestructura de evacuación, para su hibridación con el parque solar fotovoltaico existente «Tabernas I», de 48,8 MW de potencia instalada, situado en Tabernas (Almería).
The Ministry denies the El Páramo wind farm in León following an unfavorable environmental impact assessment and expiration of grid connection permits.
Wind farm developers and renewable energy sector companies with projects under processing
Spain temporarily reduces mandatory minimum diesel reserves by an additional 6 days to stabilize the market. The measure responds to coordinated action by the I...
Petroleum operators subject to mandatory minimum security stock requirements
The environmental impact statement is approved for the expansion of the Coll del Moro and Torre Madrina wind farms in Tarragona, adding 4 wind turbines and 22 M...
Wind farm developers, local administrations of Gandesa and Batea, and renewable energy sector in Tarragona
The European Commission removes the countervailing duties that taxed solar glass imported from China. This measure potentially reduces the cost of solar panels ...
Importers of Chinese solar glass, photovoltaic panel manufacturers and solar energy sector
The European Commission removes the special tariff that burdened solar glass imported from China. Following the review, it was concluded that it is no longer ne...
Importers, solar panel manufacturers and photovoltaic installers in the EU
Greenalia withdraws from building the Nordés 67.2 MW wind farm in Galicia due to inability to obtain a connection point to the electricity grid. The Administrat...
Greenalia Wind Power Nordés SLU and Galician wind energy sector