Authorization denied for a 55 MW wind farm in Burgos by Arbequina Wind
04 Apr 2026Effective: 19 Mar 202695 views
Who is affected:
Arbequina Wind, SL, renewable energy developers and the wind energy sector in Burgos
Summary
The Dirección General de Política Energética y Minas rejects Arbequina Wind's application to build the Satola wind farm in Burgos. The 55 MW project has not obtained the required prior administrative permit.
Detailed analysis
PRO
The Dirección General de Política Energética y Minas has dismissed the prior administrative authorization application submitted by Arbequina Wind, SL, for the installation of the Satola wind farm, with a capacity of 55 MW, along with its evacuation infrastructure, in the province of Burgos. This resolution means the pr…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 19 de marzo de 2026, de la Dirección General de Política Energética y Minas, por la que se desestima la solicitud de Arbequina Wind, SL, de autorización administrativa previa de la instalación eólica Satola, de 55 MW de potencia instalada, y de su infraestructura de evacuación, en la provincia de Burgos.
La empresa Savanna Power Solar 9 renuncia a construir una planta solar de 59 MW en Huelva por incompatibilidad con el futuro AVE Sevilla-Huelva. El Ministerio a...
Promotores de energías renovables y sector fotovoltaico en Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection