Correction of Authorized Power of Elawan Olmedo II Solar Plant in Valladolid
05 Sep 2026Effective: 05 Sep 202665 views
Who is affected:
Elawan Energy Olmedo 2, SL, holder of the photovoltaic plant in Valladolid
Summary
An error in the authorization of the Elawan Olmedo II photovoltaic plant is corrected: its power changes from 50.064 MW to 49.61 MW in official documents.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines rectifies material errors in the April 2023 resolution that authorized the Elawan Olmedo II solar plant in Ramiro (Valladolid). The correction affects the installed power, which is set at 49.61 MW instead of the 50.064 MW incorrectly indicated. This rectification is m…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 8 de julio de 2026, de la Dirección General de Política Energética y Minas, por la que se corrigen errores en la de 20 de abril de 2023, por la que se otorga a Elawan Energy Olmedo 2, SL, autorización administrativa previa para la instalación fotovoltaica «Elawan Olmedo II», de 49,61 MW de potencia instalada y sus infraestructuras de evacuación, en Ramiro (Valladolid).
The CNMC establishes how remuneration will be calculated for companies that transport natural gas and operate LNG plants for the 2027-2032 period, adapting the ...
Companies holding natural gas transport facilities and LNG plants in Spain
The CNMC establishes the financial remuneration rate for regasification, transport and distribution of natural gas during the 2027-2032 period. This determines ...
Natural gas regasification, transport and distribution companies and consumers
The CNMC sets new rules for calculating how much companies that distribute natural gas charge. It includes incentives for renewable gases and network digitaliza...
Natural gas distribution companies and consumers subject to distribution tariffs
The Ministry approves the environmental report for a 26.74 MW battery system that will store energy from the Larral photovoltaic plant in Zaragoza. The project ...
Promoter Planta Solar OPDE 8 SL and administrations of Aragón and Zaragoza
The Government authorizes Redexis to build a connection to introduce renewable biomethane into the existing gas network in Zaragoza. This facilitates the use of...
Redexis Infraestructuras SL, biomethane producers and gas sector in Aragón
CIEMAT and the Madrid Fire Department agree on a joint emergency response protocol for emergencies at the facilities of the energy research center in Ciudad Uni...
CIEMAT, Madrid Fire Department and emergency personnel from both institutions