Correction of errors in the authorization of the Galatea II solar plant of 92.4 MW in Madrid
23 Apr 2026Effective: 16 Apr 2026100 views
Who is affected:
Promoting company Green Capital Development 57 SLU and landowners affected in Madrid
Summary
Errors are corrected in the resolution that authorized the construction of the Galatea II photovoltaic plant in Pezuela de las Torres and Corpa (Madrid). The installation has 92.4 MW of power and was declared of public utility.
Detailed analysis
PRO
This resolution corrects material errors detected in the prior administrative authorization and construction permit granted in March 2025 to Green Capital Development 57, SLU for the Galatea II photovoltaic plant. The installation, with 92.4 MW of power, is located in the Madrid municipalities of Pezuela de las Torres …
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 16 de abril de 2026, de la Dirección General de Política Energética y Minas, por la que se corrigen errores en la de 17 de marzo de 2025, por la que se otorga a Green Capital Development 57, SLU, autorización administrativa previa de las modificaciones y autorización administrativa de construcción para la instalación fotovoltaica Galatea II, de 92,4 MW de potencia instalada, y su infraestructura de evacuación, en Pezuela de las Torres y Corpa (Madrid), y se declara, en concreto, su utilidad pública.
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection
Naturgy Renovables withdraws its application to build a 39 MW photovoltaic plant and 20 MW battery in Valladolid. The Ministry accepts the withdrawal and closes...
Naturgy Renovables SLU and photovoltaic project developers in state processing