Authorization for 101.8 MW energy storage plant in Girona
17 Jun 2026Effective: 17 Jun 2026114 views
Who is affected:
Promoting company A Green Message SL and municipalities of Sant Julià de Ramis and Vilademuls (Girona)
Summary
A Green Message, SL is authorized to build a 101.8 MW BESS energy storage plant in Sant Julià de Ramis and Vilademuls (Girona). The facility will connect to the electricity transmission network through evacuation infrastructure at 30 kV.
Detailed analysis
PRO
The General Directorate of Energy Policy and Mines grants prior administrative authorization to A Green Message, SL for the 101.8 MW BESS Lagerung plant in Girona, processed in accordance with RD 1955/2000 and Law 21/2013 on environmental assessment. The project passed simplified environmental impact assessment with a …
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 20 de mayo de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a A Green Message, SL, autorización administrativa previa para la planta de almacenamiento de energía BESS Lagerung, de 101,8 MW de potencia instalada, y sus infraestructuras de evacuación, en Sant Julià de Ramis y Vilademuls (Girona).
The environmental impact statement is approved for a 40.8 MW solar plant in Segovia that will be combined with an already operational wind farm. The project occ...
Promoter Corporación Eólica de Valdivia SL, affected municipalities in Segovia and renewable energy sector
Two energy companies have appealed before the National Court the official average price of the electricity market for 2025. Interested parties are notified so t...
Energy sector companies with interest in the average electricity market price for 2025
The Government extends until 31 December 2026 the control over fuel prices at gas stations. Large oil companies with refineries in Spain must continue reporting...
Wholesale fuel operators with refining capacity in Spain and service stations
The environmental impact report is approved for installing lithium-ion batteries that will store energy from the Mulhacén Solar photovoltaic plant in Toledo, wi...
Promoter Mulhacen Solar SL, administrations of Castilla-La Mancha and municipalities of Esquivias and Numancia de la Sagra
Mandatory minimum services are established to maintain electricity supply during the metal sector strike in A Coruña on June 16, 17 and 30 and July 2, 2026.
Metal workers in A Coruña, electricity companies and energy consumers in the area