Summary

Red Eléctrica is authorized to build a short high-voltage overhead line in Moreruela de los Infanzones (Zamora). The 190-meter installation reinforces the electrical transmission network.

Detailed analysis PRO

The Directorate General for Energy Policy and Mines grants Red Eléctrica de España, SAU, prior administrative and construction authorization for a 400 kV double-circuit overhead line of 190 meters in Zamora, declaring it of public utility. The project passed environmental impact assessment with favorable DIA in June 20…

PRO exclusive content

Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.

Desbloquear análisis PRO Ver planes y precios

Full official title

Resolución de 3 de septiembre de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Red Eléctrica de España, SAU, autorización administrativa previa y autorización administrativa de construcción para la línea aérea de transporte de energía eléctrica 400 kV, doble circuito, entrada y salida en la SE Moreruela de la línea 400 kV Grijota-Villarino 2, en Moreruela de los Infanzones (Zamora), y se declara, en concreto, la utilidad pública.