Authorization to install energy storage batteries next to Iglesias Wind Farm in Burgos
29 Jun 2026
Effective: 29 Jun 2026
16 views
Who is affected:
Boreas Wind SL, local administrations of Burgos and electrical network operators
Summary
Boreas Wind is authorized to build a 30.3 MW battery system hybridized with the Iglesias Wind Farm in Burgos. Includes electrical evacuation infrastructure to the transmission network.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants Boreas Wind, SL prior administrative and construction authorization for a 30.3 MW BESS module to be hybridized with the Iglesias Wind Farm (70.4 MW) in Burgos. The installation includes 30 kV underground lines and expansion of the PE Iglesias 30/220 kV substati…
Full official title
Resolución de 17 de junio de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Boreas Wind, SL, autorización administrativa previa y autorización administrativa de construcción para el módulo de almacenamiento por baterías «BESS Hibridación PE Iglesias», de 30,3 MW de potencia instalada, para su hibridación con el «Parque Eólico Iglesias», de 70,4 MW de potencia instalada, y para su infraestructura de evacuación, en la provincia de Burgos.