Authorization for 38.5 MW storage battery alongside solar plant in Badajoz
13 Jun 2026Effective: 13 Jun 202662 views
Who is affected:
Enel Green Power España Solar 1 SLU and local administrations of Casas de Don Pedro (Badajoz)
Summary
Enel Green Power is authorized to add a 38.5 MW battery system to its Castilblanco solar park in Badajoz, forming a 50 MW hybrid installation.
Detailed analysis
PRO
The Directorate General for Energy Policy and Mines grants prior administrative authorization to Enel Green Power España Solar 1 to install a 38.5 MW battery storage module hybridized with the Castilblanco Solar photovoltaic park (42.299 MW), resulting in a 50 MW hybrid installation in Casas de Don Pedro (Badajoz). The…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 20 de mayo de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Enel Green Power España Solar 1, SLU, autorización administrativa previa para el módulo de almacenamiento «Castilblanco Batería», de 38,5 MW de potencia instalada, para su hibridación con el parque solar fotovoltaico existente «Castilblanco Solar», de 42,299 MW de potencia instalada, y para una parte de su infraestructura de evacuación, conformando una instalación híbrida de 50 MW de potencia instalada, en Casas de Don Pedro (Badajoz).
La empresa Savanna Power Solar 9 renuncia a construir una planta solar de 59 MW en Huelva por incompatibilidad con el futuro AVE Sevilla-Huelva. El Ministerio a...
Promotores de energías renovables y sector fotovoltaico en Huelva
The Government authorizes Gestenia Energía to build a 39.6 MW battery system next to its existing solar plant in Seville. The installation will allow better sto...
Gestenia Energía SL and renewable energy sector in Andalusia
The Government authorizes Urso Solar to build a 39.6 MW battery storage system next to its existing solar plant in Utrera. This allows solar energy to be stored...
Promoter company Urso Solar SLU and renewable energy sector in Andalusia
Spain expands the list of permitted refrigerants in refrigeration installations with two new gases. This affects companies in the refrigeration and air conditio...
Installation companies, manufacturers and maintenance providers of industrial refrigeration equipment
The Ministry authorizes Enagás Transporte del Norte to build a measurement station in Bilbao to inject biomethane produced by Metabarri into the natural gas tra...
Enagás Transporte del Norte, biomethane producers and renewable gas energy sector
The Raycore model of X-ray generating equipment is officially approved for package inspection. The authorization includes technical requirements for radiologica...
Procesos Cano SL company, importers and users of X-ray equipment for inspection