Authorization of 45 MW solar plant with batteries in Rueda de Jalón (Zaragoza) to hybridize with existing wind farm
04 May 2026Effective: 10 Mar 2026122 views
Who is affected:
Molinos del Ebro SA company and municipality of Rueda de Jalón (Zaragoza)
Summary
Molinos del Ebro SA is authorized to install a 45 MW photovoltaic module and 5 MW batteries in Zaragoza, combining them with an already existing 50 MW wind farm.
Detailed analysis
PRO
The Dirección General de Política Energética y Minas grants prior administrative authorization to Molinos del Ebro SA to build the Valdejalón photovoltaic module of 45 MW and a battery storage system of 5 MW in Rueda de Jalón, Zaragoza. The project will be hybridized with the already operational Valdejalón wind farm of…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 10 de marzo de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Molinos del Ebro, SA, autorización administrativa previa para el módulo fotovoltaico Valdejalón, de 45 MW de potencia instalada, el módulo de almacenamiento con baterías Valdejalón, de 5 MW de potencia instalada, y sus infraestructuras de evacuación, para hibridación con el parque eólico existente Valdejalón, de 50 MW, en Rueda de Jalón (Zaragoza).
Molinos del Ebro SA is authorized to install a 45 MW photovoltaic module and 5 MW batteries in Zaragoza, combining them with an already existing 50 MW wind farm...
Molinos del Ebro SA and municipality of Rueda de Jalón (Zaragoza)
Red Eléctrica de España is authorized to expand the 400 kV substation in Velilla del Río Carrión (Palencia) with a new position. It is a high-voltage electrical...
Red Eléctrica de España SAU and electrical operators in the Palencia area
Errors in the European regulation governing the internal electricity market are corrected. It affects rules on cross-border electricity trading in the EU.
Electricity operators, transmission system operators, traders and energy regulators in the EU
Authorization is granted to build a 39 MW solar plant in municipalities of Valladolid that will operate together with an already existing wind farm. The install...
Parques Eólicos San Lorenzo SLU company and affected municipalities in Valladolid
Authorization is granted for the construction of a 49.11 MW photovoltaic solar module in Valladolid that will be combined with an already operational wind farm....
Promoting company, owners of affected land and municipalities of Castromonte, Peñaflor de Hornija and Torrelobatón
The Bustatur wind farm in Las Rozas de Valdearroyo and municipalities in Burgos is declared of public utility, with 41.6 MW of power. This allows Bustatur Energ...
Promoting company Bustatur Energy SL, landowners in Cantabria and Burgos