Authorization of 55 MW energy storage plant in Girona
16 May 2026137 views
Who is affected:
Company Energía Glauco, SL and municipalities of Vilademuls and Sant Julià de Ramis (Girona)
Summary
A 55 MW energy storage plant is authorized in Vilademuls and Sant Julià de Ramis (Girona). The installation includes its evacuation infrastructure.
Detailed analysis
PRO
The General Directorate of Energy Policy and Mines grants prior administrative authorization to Energía Glauco, SL to build the Glauco Almacena storage plant, with 55.384 MW of installed capacity in the Girona municipalities of Vilademuls and Sant Julià de Ramis. This authorization is the first administrative step requ…
PRO exclusive content
Implicaciones prácticas, plazos y recomendaciones específicas para tu sector.
Resolución de 21 de abril de 2026, de la Dirección General de Política Energética y Minas, por la que se otorga a Energía Glauco, SL, autorización administrativa previa para la planta de almacenamiento de energía Glauco Almacena, de 55,384 MW de potencia instalada, y su infraestructura de evacuación, en Vilademuls y Sant Julià de Ramis (Girona).
Enagás is authorized to build a new connection in the Salamanca-Zamora gas pipeline to inject biomethane in Peleas de Abajo (Zamora). Includes project approval ...
Enagás Transporte SAU, biomethane producers and landowners in Peleas de Abajo (Zamora)
The definitive closure of two 400 kV electrical lines between Gatika and Lemoiz in Bizkaia is authorized. It affects the high-voltage electrical infrastructure ...
Red Eléctrica de España SAU and users of the high-voltage electrical network in Bizkaia
A 148 MW energy storage plant (battery) is authorized in Vilademuls and Sant Julià de Ramis (Girona). It is a key infrastructure for managing renewable energy i...
Promoting company Cadaques Directorship SL, municipalities of Vilademuls and Sant Julià de Ramis
The environmental impact statement for the Rojalinda solar park is approved, with 70.8 MW of power, located in the provinces of Murcia and Alicante. The project...
Solar park developers, energy companies and administrations of Murcia and Alicante
The value of the investment remuneration annuity for category A electrical installations in non-peninsular territories is set for 2026. It affects companies in ...
Electrical companies with category A installations in the Canary Islands, Balearic Islands, Ceuta and Melilla