Key data
| Regulation | Resolution of April 9, 2026, from the General Directorate of Energy Policy and Mines |
|---|---|
| BOE Publication | November 16, 2026 |
| Entry into force | November 16, 2026 |
| Affected promoter | Saresun Trespuntas, SL |
| Project | Photovoltaic plant «Trespuntas I», Almansa (Albacete) |
| Installed capacity | 47.25 MW |
| Category | Energy / Renewables |
| Favorable EIA | January 2023 |
| Prior authorization granted | April 2023 |
| Documentation requirements | April 2024 and July 2024 |
| Promoter objections not remedied | July 2025 |
| Result | Case file archived and loss of associated rights |
Saresun Trespuntas SL will not be able to build the photovoltaic plant «Trespuntas I» of 47.25 MW in Almansa (Albacete). The General Directorate of Energy Policy and Mines has accepted the promoter's withdrawal and has archived the case file through a resolution of April 9, 2026, published in the BOE on November 16, 2026.
The case illustrates a real risk for any renewable energy promoter in Spain: obtaining the Environmental Impact Declaration (EIA) and prior authorization is not the end of the process. If the complementary documentation required by the EIA is not provided, the case file can be archived and the rights obtained can be lost.
What does this resolution establish?
The resolution formally accepts the withdrawal by Saresun Trespuntas SL of its application for prior administrative authorization and administrative construction authorization for the photovoltaic plant «Trespuntas I» and its associated evacuation infrastructure.
The chronology of the case file is as follows:
- January 2023: The plant obtains a favorable Environmental Impact Declaration (EIA).
- April 2023: Prior administrative authorization is granted.
- April 2024: The administration requires the promoter to provide the documentation required by the EIA: favorable reports from the Junta de Castilla-La Mancha on biodiversity, landscape restoration and agro-environmental measures.
- July 2024: Second documentation requirement, without remedial response from the promoter.
- July 2025: The promoter expresses objections to the process but does not remedy the documentary deficiencies.
- April 9, 2026: The General Directorate of Energy Policy and Mines accepts the withdrawal and archives the case file.
The documents that the promoter did not provide, and which were a condition imposed by the EIA, are three favorable reports from the Junta de Castilla-La Mancha:
- Report on biodiversity
- Report on landscape restoration
- Report on agro-environmental measures
Economic and operational impact
The archiving of the case file has consequences that go beyond the cancellation of the project itself:
- Loss of authorization rights: All processed authorizations (prior and construction) become void. They cannot be recovered without initiating a new procedure from scratch.
- Risk to deposited economic guarantees: The resolution explicitly states that the archiving may have consequences on the economic guarantees that the promoter may have deposited during processing. The specific amount of these guarantees is not stated in the published resolution, but their total or partial loss is a real risk.
- Impact on shared evacuation infrastructure: The «Trespuntas I» project shares evacuation infrastructure with other projects in Albacete and Valencia. The cancellation of this node can alter the access and connection rights of those linked projects, generating uncertainty for their promoters.
- Opportunity cost: The promoter invested resources in processing a project that had passed the EIA and prior authorization, but did not reach the construction phase. All that processing cost (studies, fees, technical and legal fees) is without return.
Who does it affect?
- Saresun Trespuntas SL: Direct promoter. Loses authorizations and is exposed to the loss of economic guarantees deposited.
- Promoters of solar projects linked to the same evacuation infrastructure in the provinces of Albacete and Valencia: the cancellation of «Trespuntas I» may affect their access and grid connection rights.
- Investors and financiers of Saresun Trespuntas SL or of linked projects: must review the impact on their positions and guarantees.
- Legal and technical advisors of photovoltaic projects in processing in Spain: this case is a clear precedent of the risks of not complying with the documentary conditions of the EIA.
- Renewable energy promoters in general who have case files with pending documentation requirements to remedy.
Practical example
A solar promoter obtains in 2023 the favorable EIA and prior administrative authorization for a 47 MW park. The EIA imposes as a condition the provision of three favorable reports from the autonomous community (biodiversity, landscape and agro-environmental measures) before obtaining construction authorization.
The promoter does not provide those reports. The administration requires him in April 2024 and again in July 2024. In July 2025, the promoter alleges objections to the process but does not remedy. In April 2026, the General Directorate archives the case file.
Result: the promoter has lost more than three years of processing, associated costs (impact studies, administrative fees, professional fees), obtained authorizations and faces the possible execution of the economic guarantees deposited. Furthermore, neighboring projects that shared the evacuation infrastructure are left in a situation of uncertainty about their own connection rights.
This is exactly the scenario that has occurred with «Trespuntas I» in Almansa (Albacete).
What should companies do now?
- If you are a promoter of solar projects with favorable EIA: Immediately review what documentary conditions your EIA imposes and if you have pending documentation requirements to respond to. Do not wait for a second requirement.
- If you have projects linked to the evacuation infrastructure of «Trespuntas I» in Albacete or Valencia: Contact the General Directorate of Energy Policy and Mines to assess the impact on your access and grid connection rights.
- If you are an investor or financier of Saresun Trespuntas SL: Request information on the status of the economic guarantees deposited and possible avenues for claims or recovery.
- If you have case files with unresolved requirements: Act before the administration archives the case file. Once the withdrawal is accepted or the archiving is declared, recovering rights requires initiating the procedure from scratch.
- For advisors and managers of renewable projects: Use this case as a reference to establish internal protocols for monitoring documentary conditions imposed by EIAs in all active case files.
Frequently asked questions
What documentation did Saresun Trespuntas SL not provide and why was the case file archived?
The promoter did not provide the three favorable reports required by the Environmental Impact Declaration (EIA): the report from the Junta de Castilla-La Mancha on biodiversity, the one on landscape restoration and the one on agro-environmental measures. After two requirements (April and July 2024) without remedy, and after expressing objections in July 2025 without correcting the deficiencies, the General Directorate of Energy Policy and Mines accepted the withdrawal and archived the case file on April 9, 2026.
What are the consequences of archiving the case file for the economic guarantees deposited?
The resolution explicitly states that the archiving of the case file may have consequences on the economic guarantees that Saresun Trespuntas SL may have deposited during processing. The specific amount is not stated in the published resolution, but the total or partial loss of those guarantees is a real risk arising from the withdrawal.
How does the cancellation of «Trespuntas I» affect other solar projects in Albacete and Valencia?
«Trespuntas I» shares evacuation infrastructure with other projects in the provinces of Albacete and Valencia. The cancellation of this project may alter the access and grid connection rights of those linked projects. Affected promoters should contact the General Directorate of Energy Policy and Mines to assess the specific impact on their case files.
Can Saresun Trespuntas SL request authorizations for «Trespuntas I» again?
Yes, technically it can submit a new application, but it would have to initiate the administrative procedure from scratch: new application for prior authorization, new environmental processing and new EIA. The authorizations already obtained (EIA from January 2023 and prior authorization from April 2023) have become void with the archiving of the case file.
What practical lesson does this case leave for solar energy promoters in Spain?
Obtaining the favorable EIA and prior administrative authorization does not guarantee the project. The documentary conditions imposed by the EIA (in this case, reports on biodiversity, landscape restoration and agro-environmental measures from the Junta de Castilla-La Mancha) are obligations that must be fulfilled before construction authorization. Failing to do so, even after two administrative requirements, can lead to the archiving of the case file and the loss of all processed rights.
Official source
Consult complete regulation in official source (BOE-A-2026-23979)
Notice: This article is for informational purposes only and does not constitute legal advice. For specific decisions, consult a qualified professional. Source: https://www.boe.es/diario_boe/txt.php?id=BOE-A-2026-23979