Key data
| Regulation | Resolution of November 17, 2026, from the CNMC Board, summoning interested parties in administrative litigation 4/1323/2026 |
|---|---|
| Publication in BOE | November 27, 2026 |
| Entry into force | November 27, 2026 |
| Deadline to appear | 9 business days from 27/11/2026 |
| Judicial body | Section 4 of the Administrative Litigation Chamber of the National Court |
| Procedure number | 4/1323/2026 (ordinary procedure) |
| Appellant | Regsiti Comercializadora Regulada, SLU |
| Challenged resolution | CNMC Resolution of July 16, 2026 on settlement criteria for April 28-29, 2025 |
| Category | Energy |
| Year | 2026 |
The system operator's settlements for April 28-29, 2025, the days of Spain's historic power outage, are now under judicial scrutiny. Regsiti Comercializadora Regulada, SLU has filed an administrative litigation action before the National Court against the CNMC Resolution of July 16, 2026, which established the criteria for settling those days. The CNMC Resolution of November 17, 2026, published in the BOE of November 27, 2026, formally summons all interested parties to appear if they deem it appropriate.
The outcome of this legal action may alter the settlements already executed, with direct economic consequences for any agent that participated in the electricity market during those 48 critical hours.
What does this regulation establish?
The CNMC resolution does not resolve the merits of the case: its function is to formally notify the summons to all potential interested parties so they can appear as defendants in the judicial proceeding already initiated.
The structure of the conflict is as follows:
| Element | Detail |
|---|---|
| Originating fact | Power outage in Spain on April 28-29, 2025 |
| Challenged act | CNMC Resolution of July 16, 2026: settlement criteria for the system operator for those days |
| Who appeals | Regsiti Comercializadora Regulada, SLU |
| Before whom | Section 4, Administrative Litigation Chamber, National Court |
| Type of procedure | Ordinary procedure 4/1323/2026 |
| What is summoned | All interested parties to appear as defendants |
| Deadline | 9 business days from publication in BOE (27/11/2026) |
In essence, the CNMC acts here as the main defendant party, but any market agent that has a legitimate interest in maintaining (or modifying) the settlement criteria can and should consider appearing in the proceeding.
Economic and operational impact
The April 28-29, 2025 power outage was an unprecedented event in the Spanish electricity system. The settlement criteria established by the CNMC for those days determine who receives what and who pays what in the wholesale market: deviations, adjustment services, technical restrictions and capacity payments, among other concepts.
If the legal action succeeds and the National Court annuls or modifies the resolution of July 16, 2026, the settlements already made could be revised. This implies:
- Additional payments for agents that received less than what would correspond to them under alternative criteria.
- Refunds or additional charges for agents that received more than what would result from different criteria.
- Accounting uncertainty while the proceeding is open: affected settlements may be suspended or subject to revision.
- Legal and management costs arising from participation in the judicial proceeding.
The specific economic magnitude depends on the volume of energy managed by each agent during those 48 hours and the specific criteria discussed in the legal action. There are no published figures in the summons resolution, but the impact may be relevant for any agent with a significant position in the market during the outage.
Who does it affect?
- Electricity retailers operating in the wholesale market on April 28-29, 2025.
- Generators (electricity producers) with open positions or pending settlements on those days.
- Direct market consumers with wholesale market contracts during the outage.
- Other electricity market agents (traders, aggregators, load managers) affected by the system operator's settlements for those dates.
- Regsiti Comercializadora Regulada, SLU, as the appellant party, is already represented.
Practical example
An electricity retailer that during the April 28, 2025 outage had positions in the deviation market and received an unfavorable settlement under the criteria established by the CNMC on July 16, 2026 may consider that those criteria do not correctly reflect the system situation during the outage.
If that retailer does not appear in proceeding 4/1323/2026 within the 9 business days from November 27, 2026, it will lose the opportunity to defend its position before the National Court. The court will rule without its arguments, and if the judgment modifies the settlement criteria, the agent that did not appear will not have been able to influence the outcome or how the revision is applied to its case.
Conversely, a generator that believes the CNMC's criteria are correct and that their modification would harm it also has an interest in appearing as a defendant to defend the challenged resolution.
What should companies do now?
- Identify whether your company was an electricity market agent on April 28-29, 2025. If you operated as a retailer, generator, direct consumer or other agent with settlements on those days, this legal action directly affects you.
- Review the settlements received from the system operator for those dates. Compare the amounts with the criteria established in the CNMC Resolution of July 16, 2026 to detect whether you have an economic interest in the outcome of the legal action.
- Consult with legal advisors specialized in energy law before the deadline expires. The 9 business day deadline from November 27, 2026 is strict and failure to comply means losing the right to appear in the proceeding.
- Decide whether to appear as a defendant. Both those who want to defend the current settlement criteria and those who want to challenge them through other means have reasons to consider their participation in ordinary proceeding 4/1323/2026 before Section 4 of the Administrative Litigation Chamber of the National Court.
- Make accounting provisions for the uncertainty. While the legal action is active, the settlements for April 28-29, 2025 may be subject to revision. Inform your finance department and assess whether any note in the financial statements is necessary.
Frequently asked questions
What is the deadline to appear in the legal action regarding the April 2025 power outage?
The deadline is 9 business days counted from the publication of the summons resolution in the BOE, which took place on November 27, 2026. After that deadline expires without appearing, the opportunity to participate as a defendant in the proceeding is lost.
What is proceeding 4/1323/2026 and before which body is it processed?
It is the administrative litigation action filed by Regsiti Comercializadora Regulada, SLU against the CNMC Resolution of July 16, 2026. It is processed as an ordinary procedure before the Section 4 of the Administrative Litigation Chamber of the National Court.
What CNMC resolution is being challenged in this legal action?
The CNMC Resolution of July 16, 2026 is being challenged, which established the criteria for settlement by the system operator of April 28-29, 2025, the days of the power outage in Spain.
What happens if a retailer or generator does not appear within the 9-day deadline?
If it does not appear within the 9 business day deadline from November 27, 2026, the agent loses the opportunity to defend its interests before the National Court. The court will rule without its arguments, and the judgment will be equally applicable to it without having been able to influence the outcome.
Can a company appear even if it is not the appellant?
Yes. The CNMC's summons resolution is directed precisely to all interested parties that wish to appear as defendants in the proceeding. Any electricity market agent with a legitimate interest in the outcome can participate, not just the CNMC as the main defendant party.
Official source